Acronyms Flashcards
1
Q
AC
A
Actual Cost
2
Q
ACWP
A
actual cost of work performed
3
Q
BAC
A
budget at completion
4
Q
BCWP
A
budgeted cost of work performed
5
Q
BCWS
A
budgeted cost of work scheduled
6
Q
CCB
A
change control board
7
Q
COQ
A
cost of quality
8
Q
CPAF
A
cost plus award fee
9
Q
CPF
A
cost plus fee
10
Q
CPFF
A
cost plus fixed fee
11
Q
CPI
A
cost performance index
12
Q
CPIF
A
cost plus incentive fee
13
Q
CPM
A
critical path methodology
14
Q
CV
A
cost variance
15
Q
EAC
A
estimate at completion
16
Q
EF
A
early finish date
17
Q
EMV
A
expected monetary value
18
Q
ES
A
early start date
19
Q
ETC
A
estimate to complete
20
Q
EV
A
earned value
21
Q
EVM
A
earned value management
22
Q
FF
A
finish-to-finish
23
Q
FFP
A
firm fixed price
24
Q
FMEA
A
failure mode and effect analysis
25
FP-EPA
fixed price with economic price adjustment
26
FPIF
fixed price incentive fee
27
FS
finish to start
28
IFB
invitation for bid
29
LF
late fi nish date
30
LOE
level of effort
31
LS
late start date
32
OBS
organizational breakdown structure
33
PDM
precedence diagramming method
34
PMBOK®
Project Management Body of Knowledge
35
PMIS
project management information system
36
PMP
Project Management Professional
37
PV
planned value
38
QA
quality assurance
39
QC
quality control
40
RACI
responsible, accountable, consult, and inform
41
RAM
responsibility assignment matrix
42
RBS
risk breakdown structure
43
RFI
request for information
44
RFP
request for proposal
45
RFQ
request for quotation
46
SF
start-to-finish
47
SOW
statement of work
48
SPI
schedule performance index
49
SS
start-to-start
50
SV
schedule variance
51
SWOT
strengths, weaknesses, opportunities, and threats
52
T&M
time and material
53
TQM
Total Quality Management
54
WBS
work breakdown structure