A-on-N network Flashcards

1
Q

EST?

A

earliest start time
—>determined by the activities preceding the event and is the earliest start time at which the activity on this node can start

EST(efterföljande)=EST(föregående)+duration(föregående)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

LST?

A

latest start time
—> is the same or later than the EST and is the latest time at which all the previous activities

LSD(föregående)=LSD(efterföljande)-duration(föregående)

Där LSD-finish =EST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

total float?

A
  • Difference between LST and EST

- No float time= critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The critical path?

A
  • The path that takes the longest
  • No float time=critical path
  • some activities leads to two paths, where one can be critical and the other not critical
How well did you know this?
1
Not at all
2
3
4
5
Perfectly