9 - Project Control and Performance Evaluation Flashcards
What are the basic requirements for a control system model?
Input, Output, Feedback
Describe the steps in the project control process?
Set a baseline plan
Measuring progress and performance
Comparing plan against actual
Taking action
What are some desired characteristics of a project control mechanism?
Flexible Cost effective Useful Timely Simple Adjustable Documentable
What is variance analysis?
Subtracting actual from predicted to see what the difference is
What is EVA
Earned value analysis which brings together time and cost perfomance into a monetary quantity.
What is required for earned value analysis?
Planned Value
Actual Cost
Earned Value (total planned value of task done so far/progress)
How is Cost performance index found and what does it mean?
CPI = EV/AC
>1 under budget
<1 over budget
How is Schedule performance index found and what does it mean?
SPI =EV/PV
>1 ahead of schedule
<1 behind schedule
How are new cost and time estimated?
new cost = Original cost / CPI
new time = Original time / SPI
What the main assumption of EVA to bare in mind?
It assumes linear relations
What 3 zones is the buffer usually divided into?
Monitor closely
Plan
Implement
What are some visual control examples?
Gantt chart
Taffic lights
Digital Dashboards