6 - Project Time Management Flashcards
What is the order of the six time management knowledge area processes?
- Plan schedule management
- Define activities
- Sequence Activities
- Estimate Activity Resources
- Estimate Activity Durations
- Develop Schedule
06.0 Project Time Management
What is the process of establishing the policies, procedures and documenting for planning, developing, managing, executing and controlling the project schedule?
Plan Schedule Management
06.1 Plan Schedule Management
What is the component of the project management plan that describes how the schedule will be effectively managed throughout the course of the project?
The schedule management plan
06.1.3.1 Schedule Management Plan
What component of the project management plan describes how the schedule will be effectively managed throughout the project?
The schedule management plan
06.1.3.1 Schedule Management Plan
What is the component of the project management plan that describes how the schedule will be effectively managed throughout the project?
Schedule management plan
06.1.3.1 Schedule Management Plan
What is the process of identifying the specific actions to be performed to produce the project deliverables?
Define Activities
06.2 Define Activities
Which process produces the milestone list?
Define activities process
06.2 Define Activities
In what two processes do we use the tool and technique of decomposition?
- Create WBS
- Define Activities
06.2.2.1 Decomposition
What is an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level?
Rolling Wave Planning [Progressive Elaboration]
06.2.2.2 Rolling Wave Planning
What is the comprehensive list of all scheduled activities required on the project?
The activity list
06.2.3.1 Activity List
What is an activity that does not produce definitive end products and is measured by the passage of time?
Level of Effort [LOE]
06.2.3.2 Activity Attributes
What identifies all milestones and significant points in the project?
Milestone List
06.2.3.3 Milestone List
What is similar to schedule activities, but has zero duration?
Milestone List
06.2.3.3 Milestone List
What is the process of identifying and documenting relationships among the project activities?
Sequence Activities
06.3 Sequence Activities
What are the four relationships in a PDM?
- FS = finish to start
- FF = finish to finish
- SS = start to start
- SF = start to finish
06.3.2.1 Precedence Diagramming Method
What is PDM?
Precedence Diagraming Method
06.3.2.1 Precedence Diagramming Method
What is PDM?
Precedence Diagraming Method
06.3.2.1 Precedence Diagramming Method
What is AON?
Activity on node
06.3.2.1 Precedence Diagramming Method
What is the relationship between AON and PDM?
They are the same thing
06.3.2.1 Precedence Diagramming Method
What is a method for constructing a project schedule network diagram that uses boxes for the activities and are graphically linked by lines with arrows to depict the relationships?
Precedence Diagraming
06.3.2.1 Precedence Diagramming Method
What are the four types of dependencies?
- Mandatory
- Discretionary
- External
- Internal
06.3.2.2 Dependency Determination
What allows an acceleration of a successor activity, is represented by a negative value and is represented by a minus sign?
A lead
06.3.2.3 Leads and Lags
What directs a delay in the successor activity is represented as a positive value and is represented by a plus sign?
A lag
06.3.2.3 Leads and Lags
What technique re-adjusts the leads and lags that were created in the Sequencing Activity process to create a workable schedule?
Leads + Lags
06.3.2.3 Leads and Lags
What technique allows the project team to accelerate the start of a successor activity?
Lead
06.3.2.3 Leads and Lags
What technique allows the project team to delay the start of a successor activity?
Lag
06.3.2.3 Leads and Lags
What is a lag?
A delay in a successor activity
06.3.2.3 Leads and Lags
What is the process of estimating the types and quantities of material, people, equipment, or supplies required to perform each activity?
Estimate Activity Resources
06.4 Estimate Activity Resources
What is the process of estimating the type and quantities of material, people, equipment, or supplies required to perform each activity?
Estimating activity resources
06.4 Estimate Activity Resources
What contains information regarding people, equipment, supplies and material (resources) and when they are available and unavailable?
Resource calendars
06.4.1.4 Resource Calendars
What lists the availability, capabilities, and skills of human resources?
Resource calendars
06.4.1.4 Resource Calendars