570 Who Dat Flashcards

1
Q

Responsible for developing and implementing a QA inspection repair management system

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Responsible for implementing an effective MOC process

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Responsible for QC doing repairs or alterations

A

Repair organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Assure owner - testing, inspection & examination activities meet code

A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Evaluate and except NDE examination results

A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Maintain certification records of in NDE examiners

A

Exam employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Develop an inspection plan for a piping system

A

Inspector and/or engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Also involved in making inspection plans for pipe that operates >750•F

A

Corrosion Specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Choose to conduct our RBI assessments

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Get familiar with prior inspection data and repairs prior to inspection

A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Get familiar with operating conditions and potential damage mech of pipe system

A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Perform on stream inspections

A

Inspector or tech

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Perform thickness inspection

A

Inspector or tech

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Assure individuals taking thickness measurements are trained and qualified

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Determine cause if short term corrosion rate varies significantly

A

Inspector and corrosion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Perform External Inspection

A

Inspector or qualified other

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Involved if the # of CML’s will be significantly reduced or eliminated

A

Corrosion specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Select or adjust the # of CML’s

A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Select CML’s for pipe systems subject to localized corrosion or cracking

A

Corrosion specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Determine need for non-thickness NDE techniques. Inspector consults w/:

A

Engineer or corrosion specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Determine surface prep for in DE exam. Inspector may need to consult with:

A

NDE Level III

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Perform UT flaw detection for finding linear flaws

A

NDE Examiner - Qute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Determine pressure for leak test (non-code test)

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Prior to hydrotest determine if structure will support weight

A

Engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Determine risk of brittle fracture prior to performing a pressure test
Engineer
26
Approve substituting NDE for a pressure test
NDE examiner - QUTE
27
Verify that new alloy material during repairs and alteration meet specifications
Inspector
28
When verifying new materials determine the sampling percentage
Owner
29
PMI new materials during repairs and alterations
Inspector or tech
30
If incorrect material found in existing pipe determine amount of further verification
Inspector
31
Determine date to replace incorrect materials found during PMI Survey
Inspector and owner and corrosion specialist
32
Periodically inspect components found during PMI survey that are wrong materials
Inspector
33
Determine if crack like weld flaws are the result of original weld fabrication
Inspector
34
Assess crack like flaws and environmental cracking
Engineer or corrosion specialist
35
Assess preferential weld corrosion
Inspector
36
Perform audit of owner\users to assure compliance with 570
Competent
37
Make corrections based on the audit of owners/users piping program
Owners AIA
38
Review and approve RBI assessments
Inspector and engineer
39
Determine the inspection intervals
Inspector or owner
40
Maintain a record of process fluid classification
Owner
41
PRD's tested and repaired
Exp. repair org
42
Determine the inspection intervals for PRD's
Inspector or engineer or qualified other
43
Select corrosion rate that best reflects conditions
Inspector and corrosion specialist
44
Maintain piping records
Owner
45
Review and approval an interval deferral
Inspector
46
Revise an existing interval and document basis for a change
Inspector
47
Revise an existing enterable that has unusual to degradation issues inspector and:
Engineer or corrosion specialist
48
Perform piping repairs
Repair Org
49
Authorize all repairs
Inspector
50
Authorize all alterations
Inspector and engineer
51
Designate a hold points for repairs and alterations
Inspector
52
Provide general authorization for limited or routine repairs
Inspector
53
Approve all proposed methods of design, materials, WPS's NDE and testing
Inspector or engineer
54
Approved use of on-stream welding
Owner
55
Approve repair welding of cracks
Engineer
56
Approve all repair and alteration work at hold points
Inspector
57
Approve all repair and alteration work at completion of work
Inspector
58
Design temporary repairs
Engineer
59
Determine longitudinal cracks won't grow beyond a FW patch
Engineer
60
Approve using lap patches with a material different then the pipe
Engineer
61
Determine that wall thickness is adequate for on-stream welding
Inspector
62
Allow temporary well did repairs to remain in place past "next opportunity"
Engineer
63
Allow temp leak ceiling devices to remain in place past "next opportunity"
Engineer
64
Review leak ceiling procedures
Engineer or inspector
65
Maintain a record of qualified WPS's and WPQ's
Repair Org
66
Allow exceptions to required pre-heat temperature for temporary repairs
Engineer
67
Check pre-heat temperature when using preheat in lieu of PWHT
Inspector
68
Review the use of pre-heat in lieu of PWHT
Engineer
69
Review the use of a local PWHT in lieu of a full encirclement PWHT
Engineer
70
Determine whether a pressure test is needed after repairs
Inspector
71
Approve substituting in NDE in lieu of a pressure test
Inspector and engineer
72
Overall responsibility for complying with API 570
Owner