570 Study Guide - Section 5 - Insp, Examination & Test Practices Flashcards
All in-service piping in the petrochemical industry must:
A. Have been hydrotested prior to service
B. Be built to ASME B31.3
C. Be post weld heat treat if the thickness is over 1-1/2”
D. Have an inspection plan
D. Have an inspection plan
The inspection plan for piping system should be developed by:
A. The inspector
B. The engineer
C. both the inspector and the engineer
D. either the inspector or the engineer
D. either the inspector or the engineer
When developing a piping system’s inspection plan, who should identify specific damage mechanisms and their locations?
A. Inspector
B. Corrosion specialist
C. Pressure equipment engineer
D. Either the corrosion specialist or the pressure equipment engineer
E. Either the corrosion specialist or the inspector or the equipment engineer.
B. Corrosion specialist
Whose input is required when developing an inspection plan for piping that operates at an elevated temperature?
A. Authorized inspector
B. Pressure equipment engineer
C. Corrosion specialist
D. Head office specialist
C. Corrosion specialist
A corrosion specialist should be consulted when developing inspection plans for piping that operate above:
A. 150F
B. 450F
C. 600F
D. 750F
D. 750F
Which of the following is NOT required in a piping system’s inspection plan?
A. Name of individual that will perform the inspection
B. Surface cleaning requirements
C. Type of NDE that will be used
D. Next inspection date
A. Name of individual that will perform the inspection
All RBI assessments must be conducted in accordance with:
A. API 571
B. API 579
C. API 580
D. ASME Section VIII, Div 2.
C. API 580
In the RBI process, what are the two primary factors used to determine risk?
A. Consequence of Failure and Service Class
B. Reliability and the On-stream percentage
C. Probability and Consequence of Failure
D. Inspection Effectiveness and Corrosion Mechanism
C. Probability and Consequence of Failure
Who authorizes the use of RBI assessments to set inspection intervals?
A. Authorized inspector
B. Authorized inspector and engineer
C. Owner/user
D. Corrosion Specialist
C. Owner/user
During a risk assessment, which of the following factors does NOT increase the probability of failure?
A. Volume of release
B. Age of the equipment
C. Effectiveness of the inspection program
D. Type of degradation mechanism
A. Volume of release
During a risk assessment, which of the following factors most affects the consequence of failure?
A. Type and amount of process fluid
B. Age of equipment
C. Effectiveness of the inspection program
D. Type of degradation mechanism
A. Type and amount of process fluid
Which of the following is NOT a significant factor in an RBI assessment of piping system?
A. Internal and external corrosion rate
B. All forms of cracking mechanisms
C. Piping construction code
D. Effectiveness of past inspections
C. Piping construction code
During an RBI assessment of a piping system, which of the following is NOT a significant factor that is considered to the analysis of the Consequence of Failure?
A. Health effects B. Public image C. Environmental Impacts D. Explosions E. Fires
B. Public image
All RBI assessments must be:
A. Repeated every 5 years
B. Thoroughly documented
C. Approved only by the authorized inspector
D. Conducted per guildlines in API 579
B. Thoroughly documented
If RBI assessments are used to set intervals, the assessment shall be repeated:
A. Every 5 years
B. Every 10 years
C. After each inspection
D. Once in a “blue moon”
C. After each inspection
If RBi assessments are used to set intervals, the assessment shall be repeated:
A. Every 5 years
B. Every 10 years
C. After each significant process change
D. After each significant process or hardware change
D. After each significant process or hardware change
All NDE equipment used in petrochemical facilities must:
A. Have a safety rating appropriate for all gaseous environment and the exam site
B. Be calibrated daily
C. Be used by a technician that is qualified to ASNT SNT-TC-1A
D. Have an ASME Section V approval seal
A. Have a safety rating appropriate for all gaseous environment and the exam site
Which of the following is NOT a requirement prior to performing an inspection?
A. Review previous equipment history
B. Obtain permission from the appropriate operation personnel
C. Check all the support equipment used during the inspection is safe to use
D. Be certified as an ASNT SNT-TC-1A Level 2 in VT
D. Be certified as an ASNT SNT-TC-1A Level 2 in VT
If a pipe is large enough for an internal inspection. The internal inspection should meet the requirements of:
A. API 510 B. API 579 C. API 580 D. API 2201 E. ASME Section VIII Division I
A. API 510
Who is responsible to perform the on-stream inspection of a piping system?
A. Authorized inspector
B. Examiner
C. Authorized inspector or an examiner
D. Authorized inspector or qualified others
C. Authorized inspector or an examiner
When UT thickness measurements are taken:
A. They must be taken by an examiner qualified to ASNT
B. The owner must assure competency of those taking the readings
C. The exam must be conducted with at least 100 ft-candles of light
D. A minimum of 3 readings are taken at each CML
B. The owner must assure competency of those taking the readings
UT thickness measurements may be performed by the:
A. Authorized inspector
B. Examiner
C. Authorized inspector or the examiner
D. API qualified shear wave examiner
C. Authorized inspector or the examiner
Who is responsible to perform the external inspection on a piping system?
A. Authorized inspector
B. Examiner
C. Authorized inspector or an examiner
D. Authorized inspector or qualified others
D. Authorized inspector or qualified others
Who is responsible to perform the external inspection on a piping system?
A. Authorized inspector
B. Examiner
C. Authorized inspector or an examiner
D. Authorized inspector or qualified others
D. Authorized inspector or qualified others
During the external inspection, the inspector should always:
A. Check the wall thickness at each TML location
B. Record for any unrecorded temporary repairs
C. Record the temperature of the piping system
D. Remove a part of any insulation
B. Record for any unrecorded temporary repairs
During the external inspection, the inspector should look for components that have been replaced with incorrect metallurgy. Which of the following components are most susceptible to being replaced with the wrong Metallurgy?
A. Socket-welded connections
B. Flanged components
C. Threaded components
D. Austenitic SS components
C. Threaded components