570 Study Guide - Section 8 - Repairs, Alternations & Rerating Flashcards
When repairs are conducted on a piping system, the repairs should meet the requirements of the API 570 and:
A. ASME Section VIII
B. ASME B31.3
C. ASME B31.3 or the original construction code
D. Any piping code selected by the piping engineer
C. ASME B31.3 or the original construction code
All repair and alteration work must be performed by:
A. A jurisdictional agency
B. The repair organization
C. The authorized inspection agency
D. Anyone approved by the authorized piping inspector
B. The repair organization
Before the work is started, all repair and alterations to piping systems must be authorized by the:
A. Authorized inspector
B. Pressure vessel engineer
C. Authorized inspector and the pressure vessel engineer
D. Authorized inspector or the pressure vessel engineer
A. Authorized inspector
Before the work is started, all alterations to piping systems must be authorized by the:
A. Authorized inspector
B. Pressure vessel engineer
C. Authorized inspector and the pressure vessel engineer
D. Authorized inspector or the pressure vessel engineer
C. Authorized inspector and the pressure vessel engineer
Who designs any inspection hold points required during the repair or alteration of a piping system?
A. Authorized inspector
B. Pressure vessel engineer
C. Authorized inspector and the pressure vessel engineer
D. Authorized inspector or the pressure vessel engineer
A. Authorized inspector
Who designs any inspection hold points required during the repair or alteration of a piping system?
A. Authorized inspector
B. Pressure vessel engineer
C. Authorized inspector and the pressure vessel engineer
D. Authorized inspector or the pressure vessel engineer
A. Authorized inspector
An inspector may give prior general authorization for limited or routine repairs provided that:
A. These repairs will not require a pressure test
B. These repairs will not require any NDE examinations
C. These repairs are done only to P1 or P3 materials
D. The Inspector is satisfied with the competency of the repair organization
D. The Inspector is satisfied with the competency of the repair organization
An old piping system has experienced significant corrosion. About 250’ of 8 NPS A-106 piping is being replaced. This activity must be authorized by the:
A. Authorized inspector
B. Piping engineer
C. Authorized inspector and the piping engineer
D. Authorized inspector or the piping engineer
A. Authorized inspector
An old piping system has experienced significant corrosion. The 125’ 6 NPS A-53-B piping system will be upgraded with 9 chrome piping materials. This activity must be authorized by the:
A. Authorized inspector
B. Piping engineer
C. Authorized inspector and the piping engineer
D. Authorized inspector or the piping engineer
C. Authorized inspector and the piping engineer
During alterations most of the code requirements come from:
A. API 570
B. ASME B31.3
C. ASME B31.3 or the construction code
D. The construction code
C. ASME B31.3 or the construction code
Prior to a piping system repair, all proposed NDE and testing must be approved by the:
A. Authorized inspector
B. Piping engineer
C. Authorized inspector and the piping engineer
D. Authorized inspector or the piping engineer
D. Authorized inspector or the piping engineer
Prior to a piping system repair, all proposed NDE and testing must be approved by the:
A. Authorized inspector
B. Piping engineer
C. Authorized inspector and the piping engineer
D. Authorized inspector or the piping engineer
D. Authorized inspector or the piping engineer
During piping system alterations, hold points shall be designated by:
A. The Authorized inspector
B. The piping engineer
C. Both authorized inspector and the piping engineer
D. Either the authorized inspector or the piping engineer
A. The Authorized inspector
During piping system repairs, hold points shall be designated by:
A. The Authorized inspector
B. The pressure vessel engineer
C. Both authorized inspector and the pressure vessel engineer
D. Either the authorized inspector or the pressure vessel engineer
A. The Authorized inspector
Who should approve on-stream welding of in-service piping system?
A. Authorized inspector
B. Piping engineer
C. Both the authorized inspector and the piping engineer
D. Owner/user
D. Owner/user
Weld repair of cracks that have occurred on in-service piping should not be attempted without consulting with:
A. The authorized inspector
B. The piping engineer
C. The authorized inspector and the piping engineer
D. Either the authorized inspector or the piping engineer
E. A fitness for service expert
B. The piping engineer
During repairs or alterations, who should approve work at designated hold points?
A. Authorized inspector
B. Piping engineer
C. Authorized inspector and the pressure piping engineer
D. Authorized inspector or the piping engineer
A. Authorized inspector
Once piping system repair work is complete, who should approve the finished work?
A. Authorized inspector
B. Pressure vessel engineer
C. Authorized inspector and the pressure vessel engineer
D. Authorized inspector or the pressure vessel engineer
A. Authorized inspector
Once piping system alteration work is complete, the finished work should be approved by:
A. Authorized inspector
B. Pressure vessel engineer
C. Authorized inspector and the pressure vessel engineer
D. Authorized inspector or the pressure vessel engineer
A. Authorized inspector
A 24 NPS carbon steel elbow is being replaced. Once the elbow installation is completed, who should check that the work was done correctly?
A. Authorized inspector
B. NDE examiner
C. Piping engineer
D. Either the authorized inspector or the pipe engineer
A. Authorized inspector
A new 4 NPS line is being tied into a 12 NPS schedule 160 chrome pipe. The unit startup is dependent on the completion of this work. Due to the critical timing, it is extremely important that this tie-in is in the designed location. Once the repair organization marks the tie-in location on the 12 NPS pipe, who should verify that the tie-in location is correct?
A. NDE examiner
B. Owner/user
C. Maintenance department personnel
D. Authorized inspector
D. Authorized inspector
A full encirclement welded split sleeve shall be signed by:
A. The authorized piping inspector
B. The piping engineer
C. A professional engineer
D. A fitness for service consultant or a professional engineer
B. The piping engineer
Longitudinal cracks on in-service piping systems shall not be repaired using a fillet welded patch unless:
A. Property NDE has been performed and reviewed by the authorized piping inspector
B. Property NDE has been performed and reviewed by the piping engineer
C. The all knowing piping engineer uses a crystal ball and foresees that the crack will not grown beyond the clamp
D. A piping engineer determines, without a crystal ball, that the crack will not grow beyond the clamp
D. A piping engineer determines, without a crystal ball, that the crack will not grow beyond the clamp
A deep longitudinal crack is discovered on a striaght run length of 48’ pipe. Based on expert analysis, it is expected that the crack will grow. Which of the following repairs could be performed?
A. Fillet-welded split sleeve
B. Flush patch
C. Non-welded pipe clamp
D. Non-welded clamp with stays to account for axial forces
B. Flush patch