570 Study Guide - Section 4 - Owner User Organziation Flashcards

1
Q

Who is responsible to ensure that all of the requirements of API 570 are met?

A. Authorized inspector
B. Jurisdiction
C. Fabricator
D. Owner/User
E. Piping Engineer
F. Pressure Equipment Department Manager
A

D. Owner/User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who is responsible to ensure that the authorized inspection agency functions in accordance with the requirements or API 570?

A. Authorized Inspector
B. Jurisdiction
C. Owner/User
D. Pressure Equipment Department Manger

A

C. Owner/User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

An integrity operating window is:

A. A list of process parameters that could affect equipment integrity
B. The time period allowed for a turnaround
C. The time period allowed before an inspector must recertify
D. The hole cut in pressure equipment when installing a flush patch
E. Made by Anderson windows in the USA

A

A. A list of process parameters that could affect equipment integrity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which of the following are integrity operating envelopes?

A. Only design pressure & temperature
B. Welding rod selection and welding travel speed
C. Process parameters like velocity, ph, temperature, flow rate
D. Time between minimum and maximum equipment intervals
E. Any shipping envelop provided by UPS as contrasted with the USPS

A

C. Process parameters like velocity, ph, temperature, flow rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Each owner/user that uses API 570 must:

A. Maintain a quality assurance inspection/repair management system
B. Employ (direct-hire) at least one piping engineer
C. Maintain an “R” stamp for piping repairs
D. Employ (direct-hire) at least one qualified welder who can make repairs to pressure vessels.

A

A. Maintain a quality assurance inspection/repair management system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which of the followings is NOT required to be in the owners/users quality assurance inspection/repair management system?

A. Training requirements for inspection personnel
B. Calibration of NDE equipment
C. Directions on how to document inspection results
D. Specify approval process for calculations performed during vessel alterations
E. Establish vacation policy for authorized inspectors

A

E. Establish vacation policy for authorized inspectors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Who is responsible for implementing an effecting Management of Change process?

A. Authorized Inspection Agency
B. Jurisdiction
C. Owner/User
D. Pressure Equipment Engineer
E. Repair Organization
A

C. Owner/User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A MOC System should be used to review and control changes to:

A. The process
B. Hardware
C. Either the process or the hardware
E. The earth’s rotational

A

C. Either the process or the hardware

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When repairs and alternations are being conducted, which individuals or organizations is responsible for quality control?

A. Authorized Inspection Agency
B. Repair Organization
C. API 570 Inspector
D. On-site pressure equipment department

A

B. Repair Organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which of the following is NOT a role of the API 570 inspector?

A. Provide the Owner assurance that all welding meet requirements
B. Provide the Owner assurance that all NDE examinations meet requirements
C. Provide the Owner assurance that all inspections meet requirements
D. Provide the Owner assurance that all pressure testing meet requirements

A

A. Provide the Owner assurance that all welding meet requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

During in-service piping repairs, all examination results must be accepted by the:

A. NDE supervisor
B. Authorized inspector
C. Piping engineer
D. Repair organization

A

B. Authorized inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which of the following is a role for the API 570 inspector?

A. Provide solutions when welding problems occur
B. Train on-site NDE personnel
C. Authorize substitution on pre-heat in lieu of PWHT during piping repairs
D. Evaluate and accept NDE results

A

D. Evaluate and accept NDE results

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Who is responsible to maintain the certification records for NDE examiners?

A. Authorized inspector
B. Examiners employer
C. Owner/user
D. Repair organization

A

B. Examiners employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When unusual operating conditions occur on a piping system, e.g. upset conditions, operations personnel should inform:

A. Either the inspector or engineer
B. The repair organization
C. The Jurisdiction authorities
D. No one “out of site, out of mind!”

A

A. Either the inspector or engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly