5. Commercial Assessment Flashcards

1
Q

What are the 3 commercial assessment principles?

A

Cost, revenue, decision making

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How is the go/no go decision made?

A

Assess whether development profit (costs - sale value) is okay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the 5 categories of cost?

A

Land
Design
Construction
Development
Financing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the 2 categories of revenue?

A
  1. Converting revenue from leased area to sale value using the cap rate
  2. Sum of outright sale prices
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What 4 things are included in LAND costs?

A
  1. Land Cost - purchase value
  2. Legal - fees for due diligence/purchase
  3. Survey - surveyor due diligence
  4. Vacant Possession - cost to have occupants vacate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What 2 things are included in DESIGN costs?

A
  1. Design team
  2. Topo, geotech, specialists
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What 5 things are included in CONSTRUCTION costs?

A
  1. Demolition
  2. Building
  3. Inflation up to construction
  4. Inflation during construction
  5. Contingency
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What percentage of TPC is generally accounted for by the building cost?

A

60-70%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What 5 things are included in DEVELOPMENT costs?

A
  1. Holding costs
  2. Real estate fees
  3. Promotion/brochures
  4. Inducements
  5. Development fee/infrastructure/conditions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How is holding costs calculated?

A

Council rates per annum * development period in years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How are inducements calculated?

A

Subtotal revenue * inducement in years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How is design team cost calculated?

A

Percentage * building estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How is inflation up to construction calculated?

A

(demolition + building) * building cost inflation * (development period - construction period)d

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How is inflation during construction calculated?

A

(demolition + building + inflation up to construction) * building cost inflation * inflation factor * construction period * 0.58

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

In the inflation during construction calculation, what is the inflation factor and 0.58 for?

A

Inflation factor - amount recovered as inflation not paid on developer’s profits
0.58 - cash flow factor as inflation wont apply to works that have been previously completed and paid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How is contingency calculated?

A

(demolition + building estimate + inflation up to construction + inflation during construction) * %

17
Q

How are real estate fees calculated?

A

Subtotal revenue * %

18
Q

What 3 things are in the FINANCING costs?

A
  1. Land
  2. Development
  3. Construction
19
Q

How do you calculate land financing cost?

A

Land cost * interest rate * [(deposit * development period) + [(1- deposit) * development period - settlement period)]]

20
Q

How do you calculate development financing cost?

A

0.5 * (design cost + development cost) * design and construction period * interest rate

21
Q

How do you calculate construction financing cost?

A

0.42 * construction cost * construction period * interest

22
Q

What do design team fees cover?

A

Core consultants, usually around 10-13%

23
Q

What is a topographical survey?

A

Land surveyor plan of levels and underground services

24
Q

What is a geotech investigation?

A

Report and ground drilling investigation analysis to determine foundation design concept and criteria

25
How is the building estimate found?
(gross building areas * applicable rates) + external works; usually prepared by cost planner/QS
26
How is contingency determined?
Based on the level of design developed at that stage eg. 10% at feasibility stage, 3-5% at construction stage
27
What are 4 common infrastructure costs required under resource consent conditions?
1. Upgrading underground sewer and stormwater pipes 2. Public road widening for designated entry lanes 3. Traffic lights to nearby intersections 4. Acoustic barriers
28
What % of building cost could specialist projects like supermarkets have for development fees and infrastructure?
30%
29
What is included in the development period?
Buying land to construction completion
30
How is revenue calculated?
(gross area * net/gross ratio * rental rates) + (number of carparks * rent per week * 52) + naming rights per year = subtotal - management costs (% * subtotal) = total revenue
31
When are feasibility reports done?
Indicative feasibility at the end of stage 2 Detailed feasibility at the end of stage 3 Updated at the end of stages 4 and 5
32
What 9 things should be included in a feasibility report?
1. Complete document describing project and findings 2. Cover 3. Executive summary 4. Contents 5. Brief/objective 6. Needs/outcome/options - demonstrate maximised value 7. Key criteria 8. Conclusions and recommendations 9 Appendix
33
What 3 aspects is development profit most sensitive to?
1. Sale cap rate 2. Rentals 3. Construction cost
34
What is probability risk analysis?
Individually analysing each input variable for a statistical tolerance; plots possible outcomes and probabilities
35
What is gearing?
Using a combination of debt and equity funds to increase developer return on equity but incurs debt risk
36
What are transferrable development rights?
Heritage buildings that cannot be demolished can sell their right to others to develop on their land