14. Construction Contracting Flashcards

1
Q

What are 7 procurement considerations?

A
  1. Project size and complexity
  2. New build vs refurbishment
  3. Stakeholder needs
  4. Developer in house expertise
  5. Consultant relationships
  6. Contractor relationships
  7. Risk transfer to others
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is single point of delivery?

A

Where one contracting party is responsible for design, approvals and construction; no split responsibility

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the benefits of single point delivery

A

Designs are cost effective and easier to deal with issues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is common for major projects in terms of contractor responsibilities?

A

Contractors accountable for detailed design and other responsibilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is common for most contracts (smaller projects)?

A

Construction only with some pre-construction contractor input

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the different contract options and when are they contracted?

A
  1. PPP (stage 1)
  2. PM Org (stages 2 and 3)
  3. D&C (stage 4)
  4. Construct only contracts (stage 5)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a PPP?

A

Public Private Partnership
Service contract with the client purchasing a service with a specified output and an exclusive license

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What does the bidder provide in a PPP?

A

Capital facility and operates under licence over that period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What happens at the end of a PPP period?

A

Ownership transfers back to the client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are 2 benefits of a PPP?

A

Cost effective and bidder is basically developer
Delivery risk away from Government

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are PPP’s mostly used for?

A

Infrastructure projects generally over $200m

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a PM Org?

A

Contract with project manager organisation who manages design, development and construction (single point delivery)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What happens when contracting is done further up the funnel?

A

Requires contractors with greater skills to managed higher risks for better rewards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What 3 contract documents are there in a PM Org?

A
  1. Contract to develop concept and manage designers
  2. Construction contract
  3. Performance specifications and fit for purpose provisions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are 4 advantages of a PM Org?

A
  1. Single responsibility and accountability
  2. Early input of building skills
  3. Focus on cost reduction and added value
  4. Overlap of design and construction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are 2 disadvantages of PM Org?

A
  1. Higher fees
  2. Relationship is important as control with one organisation
17
Q

What is a D&C?

A

Design and Construct contract - like PM Org but contract entered into at the end of developed design; developer can choose other consultants but will be under the contractor’s control

18
Q

What are 2 advantages of D&C?

A
  1. Single accountability for risk from this point on
  2. Early input of building skills - overlap of design and construction
19
Q

What are 2 disadvantages of D&C?

A
  1. Higher fees
  2. For more simple projects
20
Q

What are the 3 types of construct only contracts?

A
  1. PM consult-construct tender (project manager consultant)
  2. Construct tender (tender traditional system by architect)
  3. Construct cost +
21
Q

What are 2 advantages of a project manager consultant contract?

A
  1. Skilled project manager - time, cost, quality
  2. Single point responsibility (not accountability)
22
Q

What is 1 disadvantage of a project manager consultant contract?

A

Risks are still held by the client (but controlled)

23
Q

What is a tender traditional system by architect?

A

Architect manages consultants and contractor

24
Q

What are 2 advantages of a tender traditional system by architect?

A
  1. Limited client involvement
  2. Perceived low cost as little risk to contractor
25
Q

What are 2 disadvantages of a tender traditional system by architect?

A
  1. History of substantial variations
  2. No overlap between design and construction - takes longer and cannot add value
26
Q

What is the current major project approach?

A
  1. Indicative feasibility - engage designers
  2. Detailed feasibility and RC - negotiate fees with consultants (novation clause) and work with specialists
  3. Contractor appointment - includes design responsibility
  4. Construction - novate consultants to contractor so contractor has singular accountability
27
Q

What is a novation clause?

A

Can assign the contract to someone else eg. put designers under contractor control

28
Q

What is the development control group?

A

Like a board of directors (core project group of 8-10 people max) for the project who meet to review progress and report and different aspects