11. Risk Management Flashcards
How is property development risk best handled? (2)
- Early recognition of risk and how to handle them
- Risk progressive refinement throughout the development process
What are the 5 common developer risk mitigation measures?
- Substantial pre-leasing (70-80% target) with good tenants on long leases
- Pre-sell completed asset before commencing
- Negotiate risk taking by contractor (more than just construction risk)
- Bond or guarantee against contractor failing
- Sunset clause
What is the bond/guarantee against failing contractor used for?
Bond - money used to get a new contractor
Guarantee - parent company can pay if contractor is part of a bigger group
What is a sunset clause?
Allows the developer to cancel if the development cannot be done
Which risks should be focussed on?
Those with the highest probability and highest consequence.
How is decision making risk management?
Identifying costs and benefits and associated likelihoods to make balanced decisions
How is risk management best handled? (4)
- Early range of costs and progressive refinement
- Risks managed by those best able to influence them
- Prepare and monitor risk management plan
- Allow 20-30% profit provision
What are the 4 categories of risk and how are they measured?
- Well known and understood
- Aware of but considered unlikely
^ Assess probability and factor in to a degree - There but not identified
- The unknown
^ contingency and profit sum covers these
What are the top 3 risks to developers?
Environmental
Time delay
Land cost
What are 6 pre construction risks?
- Environmental
- Approvals
- Political
- Experience
- Market
- Feasibilities
How is environmental risk mitigated? (3)
Expert consultants
Analysing cost impacts
Contracts conditional on resolving issues
How are approvals risks mitigated? (3)
Purchase conditional on re-zoning/consent
Confirm basis of contributions
Active liaison with Council
How are political risks mitigated? (3)
Work with community
Try to address concerns
Be transparent
How are experience risks mitigated? (1)
Use experienced builders with good track records
How are market risks mitigated? (2)
Critically evaluate location
Factor deficiencies into land price