11. Risk Management Flashcards

1
Q

How is property development risk best handled? (2)

A
  1. Early recognition of risk and how to handle them
  2. Risk progressive refinement throughout the development process
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the 5 common developer risk mitigation measures?

A
  1. Substantial pre-leasing (70-80% target) with good tenants on long leases
  2. Pre-sell completed asset before commencing
  3. Negotiate risk taking by contractor (more than just construction risk)
  4. Bond or guarantee against contractor failing
  5. Sunset clause
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the bond/guarantee against failing contractor used for?

A

Bond - money used to get a new contractor
Guarantee - parent company can pay if contractor is part of a bigger group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a sunset clause?

A

Allows the developer to cancel if the development cannot be done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which risks should be focussed on?

A

Those with the highest probability and highest consequence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is decision making risk management?

A

Identifying costs and benefits and associated likelihoods to make balanced decisions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is risk management best handled? (4)

A
  1. Early range of costs and progressive refinement
  2. Risks managed by those best able to influence them
  3. Prepare and monitor risk management plan
  4. Allow 20-30% profit provision
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the 4 categories of risk and how are they measured?

A
  1. Well known and understood
  2. Aware of but considered unlikely
    ^ Assess probability and factor in to a degree
  3. There but not identified
  4. The unknown
    ^ contingency and profit sum covers these
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the top 3 risks to developers?

A

Environmental
Time delay
Land cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are 6 pre construction risks?

A
  1. Environmental
  2. Approvals
  3. Political
  4. Experience
  5. Market
  6. Feasibilities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How is environmental risk mitigated? (3)

A

Expert consultants
Analysing cost impacts
Contracts conditional on resolving issues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How are approvals risks mitigated? (3)

A

Purchase conditional on re-zoning/consent
Confirm basis of contributions
Active liaison with Council

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How are political risks mitigated? (3)

A

Work with community
Try to address concerns
Be transparent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How are experience risks mitigated? (1)

A

Use experienced builders with good track records

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How are market risks mitigated? (2)

A

Critically evaluate location
Factor deficiencies into land price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How are feasibility risks mitigated? (2)

A

Disciplined approach
Reject marginal projects

17
Q

When should risk planning be done?

A

At the end of each development stage to set the activity for the next stage

18
Q

How should risk planning be done?

A

Using risk assessing techniques like the risk matrix - list risk and categories by probability and impact

19
Q

What is the risk with compliance for BC and CCC?

A

BC - compliance taken at the date of application
CCC - compliance taken at the date of CCC
= 2 year gap

20
Q

What are 6 land risks and how can they be mitigated?

A
  1. Buying above market - advice from valuer
  2. Use restrictions - advice from planner
  3. Building title/easement restraints - advice from land surveyor
  4. Ground conditions - advice from geotech engineer
  5. Tangata whenua concerns - awareness and early consultation
  6. Environmental - advice from environmental engineer
21
Q

What are 5 design risks and how can they be mitigated?

A
  1. Does not meet objectives - ensure all understood
  2. Not the best value solution - ensure best selection chosen
  3. Does not work for all - early consultation
  4. Tangata whenua concerns - ongoing consultation
  5. Consenting - early discussions and public interest acknowledgement
22
Q

What are 6 building cost risks and how are they mitigated?

A
  1. Not fit for purpose (cost increases) - good design and detailing
  2. Overseas exchange rate changes - buy covers on futures market
  3. Inflationary costs - adopt fixed sum contract
  4. Design co-ordination and best value solutions - design/build contract, quality designers
  5. Contractor insolvency - bank bond or parent company guarantee
  6. Completed building operating costs - PPP
23
Q

What are 6 time-lease-sale risks and how are they mitigated?

A
  1. Running over programme - penalty to contractor, review progress regularly
  2. Market demand change - pre-lease before construction
  3. Tenant insolvency - rental guarantee bonds
  4. NLA total - focus during design
  5. No buyer at end/market change - pre-sell before construction
  6. Dispute with pre-sell agreement and buyer walks away - purchase put option at outset
24
Q

How are contractors given extra risk? (2)

A
  1. Manage designers for stages 4 or 5
  2. Have fixed price contracts including developed design details to meet the brief, BC and compliance
25
Q

What is the problem with contractors taking extra risk in NZ?

A

NZ contractors not equipped for this and need to manage their own risks