4A: Project Plans, Budgets, Work Stages Flashcards
1
Q
What is the general programme of a construction project?
A
- Pre-start meeting
- mobilisation period
- date of possession (responsibility of the site is transferred from client to main contractor)
- construction phase (including regular site inspections, progress meetings, valuations etc)
- Handover (which happens following practical completion)
- Rectification and maintenance period
- Final completion
2
Q
What is the general agenda of a pre-start meeting?
A
- introductions: roles, responsibilities, contact details
- project: description, site, special requirements
- Contract formalities
- Statutory matters: any legislation or by-laws, e.g. TPOs
- CDM and Health and Safety
- Contractual matters: programme, site organisation etc
- Clerk of works matters
- Consultants matters
- QS matters
- communications
- meetings
3
Q
What is the general agenda of a progress meeting?
A
- present and apologies
- minutes of last meeting
- any matters arising
- contractors, clerk of work, Consultants, and QS’s reports
- communications
- contract completion date
- AOB
4
Q
What progress certificates exist?
A
- Progress payment certificates
- practical completion certificates
- penultimate payment certificate (releases half of retention fee, normally 2.5%)
- Certificate of making good
- Certificate of final completion (releases remaining half of retention fee)
5
Q
What are the RIBA work stages?
A
00: Strategic Definition - work acquired via bid/design competition/direct appointment etc
01: Preparation and Brief
02: Concept design
03: Detailed Design
04: Technical Design (finishing with appointment of contractor)
05: Construction (finishing with practical completion)
06: Handover (finishing with final completion)
07: In Use