4. Contract Administration and the Construction Process Flashcards
What are the stages involved in the construction phase/
- Pre-start meeting
- Mobilisation Period
- Date of possession
- Construction Phase (including regular site inspections, progress reports and meetings, valuations)
- Handover (practical completion, start of rectification/maintenance period) – practical completion certificate (or partial/non completion)
- Rectification period (defects liability) and Maintenance period
- Final completion (end of rectification/maintenance period)
What are some typical contents of a pre-start meeting?
Introductions, contract formalities, CDM/health and safety, general procedures and site information, communication procedure, future meetings.
If more trees were delivered to site than is in the spec, what would you do?
Firstly work out who was at fault (supplier, contractor, QS, landscape architect); they will be liable to pick up any additional costs. BoQ takes precedence.
What are the advantages of having a programme of works?
Keeps the project on schedule, has better financial control (client knows what they pay and when), everyone knows what they need to do and in which order, sourcing materials on time, appointing specialists/resources in time, better time efficiency, improves worker safety.
Crucial to landscape architects, you can plan works around planting season.
What are acceptable reasons for an extension of time?
Unforseen adverse weather, exceptional circumstances such as the covid pandemic or terrorism.
If more trees were delivered to site than is in the spec, what would you do?
Firstly work out who was at fault (supplier, contractor, QS, landscape architect); they will be liable to pick up any additional costs. BoQ takes precedence.
What is “construction”?
Construction work means the carrying out of any building or engineering work including demolition, dismantling or decommissioning work.
Roles on a construction project: Who makes up the client team?
- Client
- Landscape Architect (unless they have been novated)
- Contract administrator
- Quantity surveyor
- Clerk of Works
In a construction project, what is the CLIENT’s role?
It is the client’s role to:
- make decisions relating to the scheme and its construction (or appoint others to do so)
- Decide on budget and timescales
- Appoint the design team
- signing legal documents such as contracts
- appoint a CDM coordinator
- Pay invoices from both client team and contractor
In a construction project, what is the LANDSCAPE ARCHITECT’S role?
It is the LA’s role to…
- Advise client on appointing a contractor, and any appropriate sub-contractors
- Prepare any relevant contract documents and carry out contract administration (if no contract administrator)
- Provide technical information as agreed in the contract
- Visit site to inspect quality and progress
In a construction project, what is the CONTRACT ADMINISTRATOR’S role?
It is the Contract Administrator’s Role to…
- Issue change control procedure - instructions, variations
- Issue progress certificates, such as certificate of final completion, practical completion, making good, non-completion, payment certificates.
- Chair progress meetings and issue progress reports
- Agree procedures for testing and reporting defects
- Advise client on appointing a contractor
- Contract Administration during operations on Site
- Visit site to inspect quality and progress
- Make periodic finance and progress reports
- Issue instructions and variations
- Issue payment certificates and progress certificates (including certificate of partial or final completion)
- Chair meetings
In a construction project, what is the PROJECT MANAGER’S role?
It is the project manager’s role to…
- Represents and acts on behalf of the client
- Manages and coordinates the different disciplines / contractors involved
- provides an independent service
In a construction project, what is the QUANTITY SURVEYOR’S role?
It is the QS’s role to…
- Prepare the BoQ
- Prepare pre-tender estimates
- Check tenders and produce tender report
- Advising on general financial aspects of the project
- Involved in any change in design (variation) during the construction phase
- measuring works carried out on site and periodically valuing all material on site
- Produce monthly cost reports
- Agree the final account
In a construction project, what is the CLERK OF WORKS’ role?
It is the Clerk of Works’ role to…
- inspect materials and workmanship
- Can issue verbal instructions on site (to be confirmed by relevant designer e.g. LA within two days)
- daily diary (e.g. weather report)
- Provide weekly progress reports
- attend site progress meetings
- They are generally the eyes and ears of the wider client design team, monitoring progress, quality, ecological compliance etc.
Roles on a construction project: Who makes up the contractor team?
- Main Contractor
- Site agent / manager
In a construction project, what is the MAIN CONTRACTOR’S role?
It is the main contractor has the following roles…
- carrying out the work in accordance with the contract
- proving goods, materials and workmanship
- complying with all statutory and health and safety requirements
- prepares and manages the programme
- coordinates work of all sub-contractors and suppliers
- giving notice of delays
- provide relevant insurance and other certificate
- making good any defects
- paying wages of their workers
What is the concept of Agency?
This is when the client appoints landscape architect to act as their agent, for example, setting up a contract between the client and contractor
Extent of authority and the degree of liability is controlled by the type of agency - Every act the agent performs within their scope of authority is legally binding for the client
What is the contract administrator’s role under the JCLI contract?
Same as normal - manages the contract, issues certificates, grant extensions of time, etc. In the JCLI contract, the landscape architect may act as the contract administrator.
What is novation?
It is a process whereby the contractual responsibilities of the client gets transferred to a third party, usually the main contractor - basically you stop working directly for the client and start working for the contractor. It can be beneficial in cost saving, but can reduce overall quality of the project due to value engineering.
What is a pay less notice?
A pay-less notice can follow an interim certificate to allow the client to pay the contractor less than the amount stated on the certificate, due to things like less work being done, or loss of materials, or lack of quality.
Is the retention fee always 5%?
Usually 5%: 2.5% is released at practical completion and 2.5% at final completion. It can be other amounts - but will always have to be specified in the contract.