3.8.9 Distribution Systems - Operating Flashcards
3.8.9 Train A and Train B AC, DC, and AC vital instrument bus electrical power distribution subsystems shall be OPERABLE
Applicability: ???
Modes 1, 2, 3, and 4
3.8.9
A. One AC electrical power distribution subsystem inoperable
A.1 Restore AC electrical distribution subsystem to OPERABLE status. (8 hours)
3.8.9
B. One AC vital instrument bus electrical power distribution subsystem inoperable
B.1 Restore AC vital instrument bus electrical power distribution subsystem to OPERABLE status (2 hours)
3.8.9
C. One DC electrical power distribution subsystems inoperable
C.1 Restore DC electrical power distribution subsystem to OPERABLE status (2 hours)
3.8.9
D. Required Action and associated Completion Time not met
D.1 Be in mode 3 (6 hours)
AND
D.2 Be in mode 5 (36 hours)
3.8.9
E. Two or more inoperable distribution subsystems that result in a loss of safety function.
E.1. Enter LCO 3.0.3 (immediately)