The required Train A and Train B inverters shall be OPERABLE.
Note: ??
Applicability: ??
Note: One inverter may be disconnected from its associated DC bus for <24 hours to perform an equalizing charge on its associated battery, provided:
A. The associated AC vital instrument bus is energized from its Class 1E constant voltage source regulator; and
B. All other AC vital instrument buses are energized from their associated OPERABLE inverters.
Applicability: Modes 1, 2, 3, and 4
3.8.7
A. One required inverter inoperable
A.1 Note: Enter applicable Conditions and Required Actions of LCO 3.8.9 “Distribution Systems - Operating” with any vital instrument bus be-energized.
Restore inverter to OPERABLE status (7 days)
3.8.7
B. Required Action and associated Completion Time not met.
B.1 Be in Mode 3 (6 hours)
AND
B.2 Be in Mode 5 (36 hours)
3.8.7 Bases
Planned inverter maintenance or other activities that require entry into Required Action A.1 will not be undertaken concurrent with the following: ???
A. Planned maintenance on the associated Diesel Generator: or
B. Planned maintenance on another RPS or ESFAS channel that results in that channel being in a tripped condition.