3.3.4 Critical path analysis Flashcards
1
Q
What is Critical path analysis?
A
is a technique used to identify the order in which all activities need to be completed when planning a complex project.
2
Q
What is The earliest start time (EST)?
A
the earliest the following activity can possibly start.
3
Q
What is The latest finish time (LFT) ?
A
the latest an activity can finish without delaying the whole project.