3.3.4 Critical Path Analysis Flashcards

1
Q

What is critical path analysis?

A
  • A project management tool that uses network analysis to plan complex & time-sensitive projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does critical path analysis show?

A
  • The order in which activities must be completed
  • The longest path of project activities to the completion of the project
  • The earliest & latest that each project activity can start & finish without delaying completion of the project as a whole
  • Activities within a project that can be carried out simultaneously are identified
  • The critical project activities which if delayed will cause the project as a whole to over-run
  • The shortest time possible to complete the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the 3 elements when drawing critical path analysis?

A

Node- circle that represents a point in time where an activity is started or finished
- The node is split into three sections- The left half of the circle is the activity number
- The top right section shows the earliest start time (EST) that an activity can begin based on the completion of the previous activity
- The bottom right section shows the latest finish time (LFT) by which the previous activity must be completed

Activities- a process or task within a project that takes time
Activities are shown on the network diagram as a line which link nodes
A description of the activity or a letter representing the activity is usually shown above the line

Duration- the length of time it takes to complete an activity
duration is shown as a number of time units such as hours or days below the activity line

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is float time?

A
  • When there is a difference between the earliest start time and the latest finish time (spare time)
    Where float time is identified managers may:
  • Transfer resources such as staff or machinery to more critical activities (other jobs)
    Allow extra time to complete tasks to improve quality or allow for creativity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the limitations of critical path analysis?

A
  • Very lengthy or complex projects involve a very large number of activities that have numerous dependencies–> Layers of supervision may be required to manage different groups of activities within the project
  • Network analysis often relies on estimates and forecasts–>Significant research is required prior to the completion of network analysis
    Close & honest working relationships with suppliers are essential
  • Network analysis does not guarantee the success of a project –>Project managers will need to be highly skilled & will need experience of working with complicated plans
How well did you know this?
1
Not at all
2
3
4
5
Perfectly