The U.S. Geological Survey uses the 1:24,000 scale.
1:24,000 means that 1 inch represents ________ linear feet
2,000 linear feet
1:62,500 means that 1 inch represents _____ miles.
0.98
1 mile = ________ feet
5280’
____% slope = no drainage, not suited for development;
____% slope = no problems, ideal for all types of development;
____% slope = slight problems for large commercial areas; acceptable for residential;
____% slope = major problems for commercial/industrial/large scale residential;
____% slope = suitable only for specially designed development.
0-0.5% = no drainage, not suited for development;
0.5-1% = no problems, ideal for all types of development;
1-3% = slight problems for large commercial areas; acceptable for residential;
3-5% = major problems for commercial/industrial/large scale residential;
5-10% = suitable only for specially designed development.
The three basic types of map projection are __________
conic, cylindrical, and planar
The subdivision of land, or platting, first appeared in the United States in _____.
1660.
A plat is a map of a tract or parcel of land.
A ______ allows for lots to be subdivided further or added back together.
An ______ corrects errors or adds additional information to a plat.
A _______ allows for a plat to be terminated prior to the selling of any lots.
- replat
- amending plat
- vacating plat
A _____________ is a to-scale mechanical drawing with precise topography and prescribed intervals showing the calculated location of all lots, streets, drainage patterns, facilities, and proposed dedications.
Preliminary Plat
Final plat
A final plat is the approved preliminary plat with all bearing, monuments, curves, and notations, together with all dedications, easement, and approvals.
Performance Bonds
- A performance bond is an agreement between the property owner and the community to ensure that the final plat is built as shown on the drawings within a certain time period.
- If the developer fails to meet the requirements, the government may use the bond to cover the cost of constructing the improvements.
- The bond is released once the improvements are in place and have been inspected by the local government.
____________ are gifts of land for public purposes, such as roads, parks, and utilities.
Dedications
Impact fees
Impact fees are typically charged for off-site infrastructure needed to provide service to a development, such as a water or a sewer main.
Subdivision Bonus
A subdivision bonus is the extension of development benefits beyond those normally offered in exchange for enhancements such as affordable housing, cluster housing, and open space preservation. The developer may receive assistance with infrastructure, impact fees may be waived, or the ability to construct at a higher density may be granted.
Zoning, in its simplest form, is the ___________________. Zoning is implemented through locally enacted legislation that regulates and controls the use of private property.
Separation of land uses or functions into separate districts (or “zones”)
To plat a property, the following (5) steps must be taken:
- Applicant submits a preliminary plat;
- Preliminary plat is reviewed by staff for compliance with subdivision regulations;
- Plat is then reviewed by the planning commission;
- Once the preliminary plat is approved by the planning commission, the property owner prepares the final plat;
- Final plat then repeats the process above until it is approved by the planning commission.