0POP03-ZG-0008 Power Operations Flashcards
- 0POP03-ZG-0008 Power Operations*
- *
If the operator changes feedwater flow, how long must he wait to raise Rx Power using U1118?
1 hour
- 0POP03-ZG-0008 Power Operations*
- *
With regards to the controlling Main Turbine Governor valve (normally GV #4), when must power ascension to 100% RTP be halted?
60% Open
If limited only by GV position, next step allows you to continue to raise power to 100% GV open.
- 0POP03-ZG-0008 Power Operations*
- *
When coastdown operations are in progress, what parameters should be maintained?
Tavg within ± 1.5 ˚F of Program Tavg
AFD Oscillations ≤ 1.0% peak to peak
Control Bank D 240 - 250 steps
- 0POP03-ZG-0008 Power Operations*
- *
Who must be notified when the MG VR is placed in Manual?
STP Coordinator
Transmission and Distribution Service Provider (TDSP)
Notify within 30 minutes with expected duration (Use 72 hr is time is unknown)
Note:
Must also notify if there is a change in the reactive capability of the MG.
- 0POP03-ZG-0008 Power Operations*
- *
During coastdown operations, what is the administrative limit for the + AFD Limit?
0.5% < Tech spec limit
AFD will become 0.6% more positive for every 1% of power reduction. (Assumes no rod motion)
- 0POP03-ZG-0008 Power Operations*
- *
What is the target RTP for Units 1 and 2?
- *3852 MWt**
- 2 hr average ≤ 3853 MWt*
- 0POP03-ZG-0008 Power Operations*
- *
What are some ways to lower secondary plant efficiency to give the main turbine controlling GV some bite?
HP GVs for SGFPTs
HP Main Turbine / MSR crossunder drains
Blowdown Flash Tank Vent
FW-MOV-108 FW Heater 11A/B Bypass Isolation MOV
- 0POP03-ZG-0008 Power Operations*
- *
During coastdown operations, how long should the operators wait between power reductions?
12 hrs
Xenon concerns
- 0POP03-ZG-0008 Power Operations*
- *
If RCS boron lowers to < 200 ppm, how is the RCS then diluted further?
BTRS
- 0POP03-ZG-0008 Power Operations*
- *
When should coastdown operations begin?
RCS Boron 5 ppm
OR
Deemed necessary by Operations Plant Manager
- 0POP03-ZG-0008 Power Operations*
- *
When reducing power, when can the MG placed in IMP IN?
98% RTP
- 0POP03-ZG-0008 Power Operations*
- *
What should the Tavg band be maintained at during steady state and transient conditions?
- Steady State:*
- *± 0.5 ˚F of Program Tavg**
- Transient Conditions:*
- *± 1.5 ˚F of Program Tavg**
Auctioneered High Tavg should be used as the controlling Tavg channel.