0POP03-ZG-0004 Rx Startup Flashcards
- 0POP03-ZG-0004 Rx Startup*
- *
If the Rx has been shutdown for > 60 days, what must the PR High Flux Trip Setpoint be lowered to?
85% RTP

- 0POP03-ZG-0004 Rx Startup*
- *
What must be done if any of the following conditions occur?
- Improper group alignment
- DRPI and group step counter disagree by > ± 12 steps
- Improper bank overlap
Insert all control banks
Terminate Rx Startup

- 0POP03-ZG-0004 Rx Startup*
- *
What must the operator be aware of when withdrawing S/D Banks C,D, or E?
No Rod Speed indication on CP005

- 0POP03-ZG-0004 Rx Startup*
- *
What does the Rod Control Startup Switch reset?
- POSSUM:*
- *P/A Converter**
- *Bank Overlap Unit**
- *Step Counters**
- *Slave Cyclers**
- *Urgent Failures**
- *Master Cycler**

Located on CP005.
- 0POP03-ZG-0004 Rx Startup*
- *
While less than the POAH, how many operator controlled reactivity changes are allowed to happen at once?
One at a time

- 0POP03-ZG-0004 Rx Startup*
- *
If BOTH SR channel count rates rise unexpectedly by a factor of two (2) during a Rx Startup, what must be done?
- *Insert all control rods fully into core**
- Both S/D and control banks*

Notify Rx Engineering
- 0POP03-ZG-0004 Rx Startup*
- *
What must be done if criticality is achieved before the RIL? (Control Bank C at 65 Steps)
Emergency Borate
Manually Insert all control banks

- 0POP03-ZG-0004 Rx Startup*
- *
When does the Bank Insert Lo-Lo and Bank Insert Lo annunciators extinguish?

- Bank Insert Lo-Lo:*
- *Control Bank C @ 65 Steps ± 3**
- Bank Insert Lo:*
- *Control Bank C @ 75 Steps ± 3**

- 0POP03-ZG-0004 Rx Startup*
- *
What must be done if ICRR data from three consecutive rod withdrawals predict criticality below Rod Insertion Limit of 65 steps on Bank C?
- *Manually insert all Control Banks into core**
- Not S/D Banks*

Notify Rx Engineering
Notify Unit Operations Manager
- 0POP03-ZG-0004 Rx Startup*
- *
What must be done if a RCS boron sample is VERIFIED to deviate from Estimated Critical Boron Concentration by > 20 ppm?
- *Manually insert all Control Banks into core**
- Not S/D Banks*

Notify Rx Engineering
Notify Unit Operations Manager
- 0POP03-ZG-0004 Rx Startup*
- *
What must be done if the time since Rx S/D is < 80 hrs, AND the time between the expected criticality and time used for the ECP differ by > 1 hr?
- *Manually insert all Control Banks into core**
- Not S/D Banks*

Notify Rx Engineering
Notify Unit Operations Manager
- 0POP03-ZG-0004 Rx Startup*
- *
IF ICRR data from previous rod withdrawals consistently AND unexpectedly predicts criticality at a Control Bank position outside ECP +500 pcm band OR All Rods Out condition, what must be done?
Stop the Rx S/U
Notify Unit Operations Manager
Rx Engineering and SM must evaluate cause
- *If cause cannot be determined in 1 HOUR, then manually insert all control banks into the core**
- Not S/D Banks*
- Note:*
- Same actions if Control bank position outside ECP -500 pcm band but above the minimum insertion limit of Control Bank C at 65 steps.*

- 0POP03-ZG-0004 Rx Startup*
- *
What must be done if Tavg drops below 561 ˚F during a Rx Startup?
- Approach to Criticality:*
- *Trip the Rx**
- Rx Critical:*
- *Tech Spec 3.1.1.4 (15 min to restore)**
If Tavg cannot be restored, trip the Rx

- 0POP03-ZG-0004 Rx Startup*
- *
What parameters must be recorded for critical data when the Rx is stabilized at 1x10-8 IR amps?
Rod Position
Tavg
RCS Boron Concentration

- 0POP03-ZG-0004 Rx Startup*
- *
Per 0POP03-ZG-0004 Rx Startup, when is MODE 2 entered?
Control Bank Rod Withdrawal commences

- 0POP03-ZG-0004 Rx Startup*
- *
What will cause a rod bottom alarm?

ALL S/D and control banks on bottom
- *ANY S/D rod OR Control Bank A rod on bottom**
- Occurs after ALL S/D rods on top and CB “A” 12 steps off bottom*
- *ANY Control Bank B/C/D rod on bottom**
- Occurs after respective bank 12 steps off bottom*
- Note:*
- Rod Bottom alarm will clear when all S/D rods on top and CB “A” rods 12 steps off bottom.*
- 0POP03-ZG-0004 Rx Startup*
- *
If ICRR unexpectedly predicts criticality < -500 pcm position, what is the maximum amount the operator can pull control rods at a time?
25 Steps
OR
Criticality

Note:
Normally withdraw rods 50 steps at a time
- 0POP03-ZG-0004 Rx Startup*
- *
What are the prerequisites for 0POP03-ZG-0004 (Rx Startup) with regards to the following parameters?
- Tavg
- PZR Level
- PZR Pressure
- SR Counts
- Tavg:*
- *564 ˚F - 570 ˚F**
- PZR Level:*
- *20% - 30%**
- PZR Pressure:*
- *2200 psig - 2250 psig**
- SR Counts:*
- *> 2.0 cps**

- 0POP03-ZG-0004 Rx Startup*
- *
When performing a Rx startup, how many steps until bank overlaps begin?
137 steps
- Control Bank A at 137 steps, Control Bank B will begin to lift.
- Process repeated for control bank C and control bank D.
- 0POP03-ZG-0004 Rx Startup*
- *
Why is Control Bank D at 100 steps normally chosen for the ECP?
Provides adequate AFD control during ascension

Other Control Bank D positions may be used for the ECP to ensure +500 pcm is available.