0POP03-ZG-0004 Rx Startup Flashcards

1
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

If the Rx has been shutdown for > 60 days, what must the PR High Flux Trip Setpoint be lowered to?

A

85% RTP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

What must be done if any of the following conditions occur?

  • Improper group alignment
  • DRPI and group step counter disagree by > ± 12 steps
  • Improper bank overlap
A

Insert all control banks

Terminate Rx Startup

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

What must the operator be aware of when withdrawing S/D Banks C,D, or E?

A

No Rod Speed indication on CP005

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

What does the Rod Control Startup Switch reset?

A
  • POSSUM:*
  • *P/A Converter**
  • *Bank Overlap Unit**
  • *Step Counters**
  • *Slave Cyclers**
  • *Urgent Failures**
  • *Master Cycler**

Located on CP005.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

While less than the POAH, how many operator controlled reactivity changes are allowed to happen at once?

A

One at a time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

If BOTH SR channel count rates rise unexpectedly by a factor of two (2) during a Rx Startup, what must be done?

A
  • *Insert all control rods fully into core**
  • Both S/D and control banks*

Notify Rx Engineering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

What must be done if criticality is achieved before the RIL? (Control Bank C at 65 Steps)

A

Emergency Borate

Manually Insert all control banks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

When does the Bank Insert Lo-Lo and Bank Insert Lo annunciators extinguish?

A
  • Bank Insert Lo-Lo:*
  • *Control Bank C @ 65 Steps ± 3**
  • Bank Insert Lo:*
  • *Control Bank C @ 75 Steps ± 3**
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

What must be done if ICRR data from three consecutive rod withdrawals predict criticality below Rod Insertion Limit of 65 steps on Bank C?

A
  • *Manually insert all Control Banks into core**
  • Not S/D Banks*

Notify Rx Engineering

Notify Unit Operations Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

What must be done if a RCS boron sample is VERIFIED to deviate from Estimated Critical Boron Concentration by > 20 ppm?

A
  • *Manually insert all Control Banks into core**
  • Not S/D Banks*

Notify Rx Engineering

Notify Unit Operations Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

What must be done if the time since Rx S/D is < 80 hrs, AND the time between the expected criticality and time used for the ECP differ by > 1 hr?

A
  • *Manually insert all Control Banks into core**
  • Not S/D Banks*

Notify Rx Engineering

Notify Unit Operations Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

IF ICRR data from previous rod withdrawals consistently AND unexpectedly predicts criticality at a Control Bank position outside ECP +500 pcm band OR All Rods Out condition, what must be done?

A

Stop the Rx S/U

Notify Unit Operations Manager

Rx Engineering and SM must evaluate cause

  • *If cause cannot be determined in 1 HOUR, then manually insert all control banks into the core**
  • Not S/D Banks*
  • Note:*
  • Same actions if Control bank position outside ECP -500 pcm band but above the minimum insertion limit of Control Bank C at 65 steps.*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

What must be done if Tavg drops below 561 ˚F during a Rx Startup?

A
  • Approach to Criticality:*
  • *Trip the Rx**
  • Rx Critical:*
  • *Tech Spec 3.1.1.4 (15 min to restore)**

If Tavg cannot be restored, trip the Rx

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

What parameters must be recorded for critical data when the Rx is stabilized at 1x10-8 IR amps?

A

Rod Position

Tavg

RCS Boron Concentration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

Per 0POP03-ZG-0004 Rx Startup, when is MODE 2 entered?

A

Control Bank Rod Withdrawal commences

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

What will cause a rod bottom alarm?

A

ALL S/D and control banks on bottom

  • *ANY S/D rod OR Control Bank A rod on bottom**
  • Occurs after ALL S/D rods on top and CB “A” 12 steps off bottom*
  • *ANY Control Bank B/C/D rod on bottom**
  • Occurs after respective bank 12 steps off bottom*
  • Note:*
  • Rod Bottom alarm will clear when all S/D rods on top and CB “A” rods 12 steps off bottom.*
17
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

If ICRR unexpectedly predicts criticality < -500 pcm position, what is the maximum amount the operator can pull control rods at a time?

A

25 Steps
OR
Criticality

Note:
Normally withdraw rods 50 steps at a time

18
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

What are the prerequisites for 0POP03-ZG-0004 (Rx Startup) with regards to the following parameters?

  • Tavg
  • PZR Level
  • PZR Pressure
  • SR Counts
A
  • Tavg:*
  • *564 ˚F - 570 ˚F**
  • PZR Level:*
  • *20% - 30%**
  • PZR Pressure:*
  • *2200 psig - 2250 psig**
  • SR Counts:*
  • *> 2.0 cps**
19
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

When performing a Rx startup, how many steps until bank overlaps begin?

A

137 steps

  • Control Bank A at 137 steps, Control Bank B will begin to lift.
  • Process repeated for control bank C and control bank D.
20
Q
  • 0POP03-ZG-0004 Rx Startup*
    • *

Why is Control Bank D at 100 steps normally chosen for the ECP?

A

Provides adequate AFD control during ascension

Other Control Bank D positions may be used for the ECP to ensure +500 pcm is available.