Week 9-10 Flashcards
Why is it important for the operating crew to energize the switchyard loads from the Gas Turbine Generators during a Loss of Offsite Power (LOOP)?
A. Restores control power NAN-S05 and NAN-S06.
B. Restores the normal power supply to the security lighting system.
C. Ensures that switchyard breaker operation will be possible.
D. Ensures that a minimum load is placed on the GTGs allowing the generators to burn their fuel completely.
C. Ensures that switchyard breaker operation will be possible.
The Blackout ORP directs the crew to place all charging pumps in PTL to…
A. provide for controlled restoration of RCP seal injection.
B. prevent inadvertent dilution on restoration of injection flow.
C. ensure that pump suction source is aligned prior to restart.
D. ensure pumps are not immediately anti-pumped on restoration of power.
A. provide for controlled restoration of RCP seal injection.
During a Loss of Offsite Power (LOOP), the operating crews are directed to startup a Gas Turbine Generator (GTG) within 1 hour and energize NAN-S07. Assuming that each unit is being supplied by their own diesel generators, is this step still necessary, and why or why not?
A. No, this step can be omitted if at least one DG is operating on each unit.
B. Yes, this step ensures that the GTG batteries and HVAC equipment have power.
C. Yes, this step is necessary to augment the DGs, enabling one unit to startup if necessary.
D. No, this is only performed if there is thunderstorm activity in the “vicinity.”
B. Yes, this step ensures that the GTG batteries and HVAC equipment have power.
- The plant is operating at 100% power
- The normal supply breaker to PBA-S03 trips open.
- The “A” Emergency Diesel starts but does not supply power to PBA-S03.
- All other electric plant buses are energized and normal.
Which one of the following events has occurred?
A. Blackout (BO)
B. Loss of Offsite Power (LOOP)
C. Loss of Forced Circulation (LOFC)
D. Loss of Power (LOP)
D. Loss of Power (LOP)
Which one of the following most correctly describes plant conditions if the switchyard grid has de-energized, and remains so, and both diesel generators have started and are running and powering their respective 4.16kV AC class busses?
A. Blackout (BO)
B. Loss of Offsite Power (LOOP)
C. Loss of Forced Circulation (LOFC)
D. Loss of Power (LOP)
B. Loss of Offsite Power (LOOP)
During the performance of an EOP the CRS may proceed with the next step…
A. only when the current step has been completed.
B. only with SM concurrence if the current step is not completed.
C. only if the current step will be completed before subsequently assigned steps.
D. when there is reasonable assurance that the current step is proceeding satisfactorily.
D. when there is reasonable assurance that the current step is proceeding satisfactorily.
Which of the following is the MINIMUM power source necessary to maintain the unit in a safe condition AND energize switchyard loads for up to 16 hours following a Blackout?
A. Two Gas Turbine Generators.
B. One Emergency Diesel Generator.
C. One Off-Site Power Source.
D. One Gas Turbine Generator.
D. One Gas Turbine Generator.
Based on plant conditions, additional equipment operation may be required to mitigate a blackout event (above and beyond coping loads). Which of the following is an acceptable combination of loads assuming a single GTG in operation on PBA-S03?
A. AFB-P01 and CHE-P01.
B. AFN-P01 and HPSI A.
C. AFN-P01 and CHE-P01.
D. AFA-P01 and LPSI A.
C. AFN-P01 and CHE-P01.
During a LOOP, the operating crew has just completed the appropriate maintenance of vital auxiliaries success paths for power restoration. The status of electrical buses energized are as follows:
- PBB-S04 is energized from EDG B
- PNA-D25 is energized from Inverter PNA-N11
- PKA-M41 is energized from it’s battery
- PKC-M43 is energized from it’s battery
- All other buses are de-energized
The maintenance of vital auxiliaries safety function is:
A. satisfied
B. not satisfied because all energized buses are not in the same train.
C. not satisfied because PNC-D27 is not energized.
D. not satisfied because both PKA-M41 and PKC-M43 do not have their associated chargers in service.
B. not satisfied because all energized buses are not in the same train.
The Blackout coping strategy assumes that PBA-S03 will be energized from a GTG within:
A. 30 Minutes.
B. 60 Minutes.
C. 90 Minutes.
D. 120 Minutes.
B. 60 Minutes.
- The Unit has been in a blackout condition for 2 hours.
- QSPDS indicates 32 degrees superheat and has been stable for the last 15 minutes.
- CET temperatures and RCS pressure have also been stable for the last 15 minutes.
What is the condition of RCS and core heat removal?
A. All natural circulation has been lost, core uncovery has occurred.
B. Single phase natural circulation is maintaining heat removal.
C. All natural circulation has been lost, but the core still remains covered.
D. Two phase natural circulation is maintaining heat removal.
D. Two phase natural circulation is maintaining heat removal.
Which of the following describes how SDM is monitored during a blackout?
A. At 25°F Tc intervals, SDM is calculated using current Tc and boron concentration at the time of the event.
B. At 50°F Tc intervals, SDM is calculated using Tc minus 50°F and boron concentration at the time of the event.
C. At 50°F Tc intervals, SDM is calculated using current Tc and boron concentration at the time of the event minus 100 ppm.
D. At 25° F Tc intervals, SDM is calculated using Tc minus 25°F and boron concentration at the time of the event minus 100 ppm.
B. At 50°F Tc intervals, SDM is calculated using Tc minus 50°F and boron concentration at the time of the event.
Given the following conditions: Loss of offsite power. Both DGs fail to start. Which of the following describes how the safety analyses assume the reactivity control safety function is maintained?
A. Maintain the plant in Hot Standby.
B. Plant cooldown is limited to 75 degrees/hour.
C. Within 1 hour, RCS pressure is reduced below SIT pressure.
D. After verification of all CEAs inserted; cooldown to SDC entry conditions.
A. Maintain the plant in Hot Standby.
- Emergency boration is required
- RWT is below 82% level
- PC Cleanup is recirculating the RWT
Which of the following flow paths is NOT operable?
A. CHE-HV-536
B. CHB-V327
C. PCN-V215, spent fuel pool supply
D. CHN-HV-532
A. CHE-HV-536
WHICH ONE of the following requires that boration be established per 40AO-9ZZ01, “EMERGENCY BORATION”?
A. A plant cooldown has been directed by the CRS.
B. Entry into any Emergency Operating Procedure.
C. Shutdown Margin has been lost.
D. Entry into the Lower Mode Functional Recovery Procedure.
C. Shutdown Margin has been lost.