Week 6 (Job order costing) formulas Flashcards

1
Q

PDR equation ?

A

PDR =
estimated manufacturing overhead costs / estimated activity level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

applied overhead equation ?

A

applied overhead =
PDR * actual activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost of goods manufactured equation refined ?

A

cost of goods manufactured =
beginning work in process + direct materials used + direct labor + applied overhead - ending work in process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Conversion costs equation refinement ?

A

conversion costs =
direct labor + applied overhead

How well did you know this?
1
Not at all
2
3
4
5
Perfectly