Week 11 Standard costing formulas Flashcards

1
Q

DM price variance equation

A

DM price variance =
(AQ * AP) - (AQ * SP)
- AQ stands for direct materials purchased

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

DM quantity variance equation

A

DM quantity variance =
(AQ * SP) - (SQ * SP)
- AQ stands for direct materials used in production

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

DM (SQ) equation

A

DM (SQ) =
standard quantity of DM per unit * # of units produced

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

DL rate variance equation

A

DL rate variance =
(AH * AR) - (AH * SR)
- [(AH * AR) represents the actual cost of direct labor incurred]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

DL efficiency variance equation

A

DL efficiency variance =
(AH * SR) - (SH * SR)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

DL (SH) equation

A

DL (SH) =
standard hours of DL per unit * # of units produced

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Total DL variance equation

A

Total DL variance =
DL rate variance + DL efficiency variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

VOVH spending variance equation

A

VOVH spending variance =
actual variable overhead costs - (AH * SR)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

VOVH efficiency variance equation

A

VOVH efficiency variance =
(AH * SR) - (SH * SR)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

VOVH (SH) equation

A

VOVH (SH) equation =
standard hours per unit * # of units produced

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Total VOVH variance equation

A

Total VOVH variance =
VOVH spend variance + VOVH efficiency variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly