Voltage and Reactive - B Flashcards

1
Q

What is the most effective equipment for reactive reserve response to a contingency?

A. Shunt reactors
B. HVDC
C. Synchronouse condensers
D. Series capacitors

A

C. Synchronous condensers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Your system voltages are extremely high during a light load midnight period. All of your capacitors are off, all of your reactors are on and a 500 kv transmission line is loaded below its surge impedance loading. What can be done to reduce the impact of the transmission line on system voltages?

(Two answers)

A. Reduce the loading on the line some more
B. Remove the line from service if it has been pre-studied
C. Load the line above its SIL
D. Open-end the line

A

B. Remove the line from service if it has been Pre-studied

&

C. Load the line above its SIL

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The phase voltage in a wye-connected load is 277V. What is the line-to-line voltage?

A. 277 V
B. 160 V
C. 320 V
D. 480 V

A

D. 480 V

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the approximate MVAR/mile production for a 345kv overhead line?

A. 5
B. 0.75
C. 2
D. 0.33

A

B. 0.75

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Transmission Operators shall _____ and _____ reactive resources so that they can be applied effectively and quickly when contingencies occur.

A. Schedule and control
B. Concentrate and locate
C. Control and monitor
D. Disperse and locate

A

D. Disperse and locate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The MW loading on a transmission line is that the point where the natural MVAR production of the line matches the line’s MVAR usage. This MW loading point is called the

A. Characteristic impedance (CI)
B. Transmission line loading relief (TLR)
C. Surge impedance loading (SIL)
D. Natural loading (NL)

A

C. Surge impedance loading (SIL)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which of the following situation would lead to the highest Ferranti Rise?

A. A short open-ended line with a weak closed-end bus
B. A short open-ended line with a strong closed-end bus
C. A long open-ended line with a weak closed-end bus
D. A long open-ended line with a strong closed-end bus

A

C. A long open-ended line with a weak closed-end bus

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The excitation current of a generator should be adjusted…

A. To the maximize the rotor angle stability
B. Manually by the plant operator as directed by the system operator
C. By the local automatic voltage regulator
D. To minimize the MVAR losses

A

C. By the local automatic voltage regulator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Reactance in a shunt reactor will increase with the _____

A. Magnetic constant of the material that surrounds the coil
B. Number of turns in the coil
C. Diameter of the coil
D. Distance of the plates

A

B. Number of turns in the coil

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Voltage in the system should be kept within _____

A. +/- 5%
B. +/- 1%
C. +/- 10%
D. +/- 8%

A

A. +/- 5%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The actual voltage is 253kv on a 230kv line. What is the P.U. Voltage?

A. 0.95
B. 0.1
C. 1.05
D. 1.1

A

D. 1.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Transmission Operators shall direct corrective action including ______ necessary to prevent voltage collapse when reactive resources are insufficient

A. Load reduction
B. Capacitor switching.
C. Generation scheduling
D. Reactor switching

A

A. Load reduction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

To ensure a generator’s reactive reserve is available to respond to system voltage deviations, the generator’s voltage regulator should be placed in what mode of operation?

A. Manual
B. Automatic
C. Synchronous
D. induction

A

B. Automatic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Three transmission lines connect a generation source to a load area. Line#1 has an impedance of 40 ohms, line #2, 60 ohms and line #3, 40 ohms. Total power flow is initially 2000 MW, line #1 drops. Assuming no generation or load changes and neglecting losses, what will be the MW flow on line #2

A. 1000 MW
B. 2000 MW
C. 1200 MW
D. 800 MW

A

D. 800 MW

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Reactive sources should be used for ________

A. Normal operating conditions
B. Peak loading
C. Energy Alerts only
D. Normal and first contingency conditions

A

D. Normal and first contingency conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Sustained excessive current flow on an overhead line causes the conductors to sag thus _____ the ground clearance and _____ safety margins.

A. Eliminating/ Maintaining
B. Maintaining / Increasing
C. Decreasing / Reducing
D. increasing/ Decreasing

A

C. Decreasing / Reducing

17
Q

Transmission line removal as a method of voltage control can be used if _____

A. Reactive equipment is available
B. Loop flow remains high
C. Synchronous condensers are offline
D. Reliability stays at acceptable levels

A

D. Reliability stays at acceptable levels

18
Q

To avoid a high over-voltage at the Open-end of a transmission line, the switching sequence is arranged so that some load is attached to the otherwise open-end. Which type of load would best reduce this Ferranti over-voltage?

A. Capacitive load
B. Lagging power factor load
C. Leading power factor load
D. Resistive load

A

B. Lagging power factor load

19
Q

Which of the following system Elements would be considered reactive power sources?

(Two answers)

A. Generators
B. Shunt reactors
C. Transformers
D. Synchronous condensers

A

A. Generators

&

D. Synchronous condensers

20
Q

Two resisters of 10 ohms are connected in parallel. The net resistance of their combination is _____

A. 20 Ohms
B. 2.5 Ohms
C. 10 Ohms
D. 5 Ohms

A

D. 5 Ohms

21
Q

Reactive resources shall be dispersed and located _____ so that they can be applied effectively and quickly when contingencies occur.

A. Sparingly
B. Externally
C. Geographically
D. Electrically

A

D. Electrically

22
Q

Voltage reduction on a transmission system should not be attempted unless the transmission system ____

A. Is isolated
B. Is over-loaded
C. Has enough generation support
D. Is blacked out

A

A. Is isolated

23
Q

Transmission system voltages should be maintained within what percentage of nominal?

A. +/- 10%
B. +/- 5%
C. +/- 7%
D. +/- 3%

A

B. +/- 5%

24
Q

Which of the following devices would you use if you were calculating dynamic reactive reserve for your system?

A. Transformers
B. Shunt reactors
C. Generators
D. Shunt capacitors

A

C. Generators