Interchange Coordination and Scheduling - A Flashcards
Balancing Authority “A” has a 100 MW schedule export to Balancing Authority “B”, a 50 MW schedule export to Balancing Authority “C”, and a 250 MW schedule import from Balancing Authority “D”. What is the net scheduled interchange for Balancing Authority “A”?
A. -150 MW
B. 100 MW
C. 0 MW
D. -100 MW
D. -100 MW
At 1105 a unit trips offline outside of your Balancing Authority’s area. The frequency dips to 59.91. Your Balancing Authority’s ACE was zero for the hour. Assuming no metering error or time error corrections, what could be said about the inadvertent for your Balancing Authority area for HE 1200?
A. Near zero inadvertent
B. Inadvertent accumulation coming into your area
C. Inadvertent accumulation leaving your area
D. Not enough information given
C. Inadvertent accumulation leaving your area
A Transmission Service Provider has studied their system and determined that its ATC is 1000 MW from area “A” to area “B”. Assume that this Transmission Service Provider sells 500 MW of this ATC as non-firm. No other ATC is sold. What amount of firm ATC does this Transmission Service Provider have from area “A” to “A” after this 500 MW non-firm ATC sale is completed?
A. 1000
B. 0
C. 250
D. 500
A. 1000
A. Condition when a Balancing Authority, Reserve Sharing Group, or Load Serving Entity does not have adequate energy resources to provide its customers’ expected energy requirement is called:
A. An energy emergency
B. A capacity deficiency
C. A generation emergency
D. An energy deficiency
A. Energy emergency
A PSE has one of its transactions curtailed via procedure at 2100. Assuming that the curtailment is subsequently lifted, when can the PSE expect the energy profile of the transaction to return to its original value?
A. When the Transmission Provider submits a new tag
B. When the PSE chooses
C. When the Reliability Coordinator chooses
D. When the Balancing Authority submits a new or revised tag
B. When the PSE chooses
A PSE’s “Tag correction” is…
A. A change to an existing Tag that does not affect the reliability impact of the transaction
B. A change to an existing Tag that corrects the energy profile of the Tag
C. A change to an existing Tag that corrects the name of the entity who holds title to the energy
D. A change to an existing Tag that does affect the reliability impact of the transaction
A. A change to an existing Tag that does not affect the reliability impact of the transaction
An appropriate use of a pseudo-tie is to ____.
A. Pay back inadvertent
B. Off-set meter
C. Determine ATC
D. Account for joint owned generation
D. Account for joint owned generation
A PSE wants to modify an Interchange Transaction’s POD while the Transaction is in progress. What action is required?
A. The Interchange Transaction must be revised
B. No changed are required
C. The Tag must be modified when the opportunity presents itself
D. The Interchange Transaction must be terminated and a new Tag must be submitted
D. The Interchange Transaction must be terminated and a new Tag must be submitted
A Balancing Authority has two Interchange Transactions in place for the period from HE 1100 to HE 1800.. Transaction #1 is a 1000 MW import that uses a 20 minute ramp. Transaction #2 is a 400 MW import that uses a 10 minute ramp. If Transaction #1 is curtailed at 1530 with a 10 minute ramp, what is the billed MWh of the two Transactions for HE 1600.
A. 1000 MWh
B. 1100 MWh
C. 1200 MWh
D. 1400 MWh
C. 1200 MWh
Balancing Authorities Transmission Operators, and the ____ are responsible for tagged transactions and shall have facilities to receive unsolicited notification from the Tag Authority
A. IDC
B. Reliability Authorities
C. Purchase Selling Entities
D. Load Serving Entities
C. Purchase Selling Entities
An interconnection has four Balancing Authorities. The schedules for each Balancing Authority are listed below. What is the net scheduled interchange of Balancing Authority “A”?
Balancing Authority A: To Balancing Authority B 100 MW, To Balancing Authority C 50 MW, To Balancing Authority D 250 MW
Balancing Authority B: To Balancing Authority A -100 MW, To Balancing Authority C -200 MW, To Balancing Authority D 300 MW
Balancing Authority C: To Balancing Authority A -50 MW, To Balancing Authority B 200 MW, To Balancing Authority D 150 MW
Balancing Authority D: To Balancing Authority A -250 MW, To Balancing Authority B -300 MW, To Balancing Authority C -150 MW
A. -700 MW
B. 400 MW
C. 300 MW
D. 500 MW
B. 400 MW
Balancing Authority A has the following schedules implemented. What is the Balancing Authorities scheduled net interchange? Import from Balancing Authority B 100 MW, Import from Balancing Authority C 200 MW, Export to Balancing Authority D 800 MW
A. 1000 MW Import
B. 1100 MW Export
C. 500 MW Export
D. 500 MW Import
C. 500 MW Export
An Interchange Transaction is stopped after it has been implemented. The correct terminology is that this Interchange Transaction is:
A. Cancelled
B. Eliminated
C. Terminated
D. Altered
C. Terminated
An Interchange Transaction is not implemented until it is incorporated into
A. The OASIS system
B. The Balancing Authurities net scheduled interchange
C. The ISN
D. The Balancing Authorities net actual interchange
B. The Balancing Authorities net scheduled interchange
Balancing Authority A sells 100 MW to adjacent Balancing Authority B. The schedule begins at the top of the hour and is ramped for 10 minutes. How much energy is actually transferred in that hour?
A. 88 MWh
B. 90 MWh
C. 92 MWh
D. 94 MWh
C. 92 MWh