Transmission Operations - B Flashcards
Three transmission lines connect a generation source to a load area. Line #1 has an impedance of 40 ohms, line #2 = 60 ohms, and line #3 = 40 ohms. Total power flow is initially 1000 MW. Assume that line #1 trips. Assuming no generation or load changes and neglecting losses, what will be the MW flow on line #2?
A. 600 MW
B. 800 MW
C. 1000 MW
D. 400 MW
D. 400 MW
Responding to operating security limit violations is necessary only when:
A. Violations occur or are expected to occur.
B. It may lead to voltage collapse.
C. There is a reduction in the amount of Interchange Transactions.
D. It will cause cascading outages.
A. Violations occur or are expected to occur
If a Transmission Operator has an anticipated emergency condition, it shall inform _______
A. Its Balancing Authority and Load Serving Entity
B. Its reliability Coordinator and any other potentially affected Transmission Operators
C. Its Generator Operator and Balancing Authority
D. Its Purchase Selling Entity and Interchange Authority
B. Its Reliability Coordinator and any other potentially affected Transmission Operators
Three transmission lines connect a generation source to a load area. Line #1 has an impedance of 100 ohms, line #2 = 50 ohms, and line #3 = 50 ohms. Total power flow is initially 1000 MW. Assume that line #1 trips. Assuming no generation or load changes and neglecting power losses, what will be the MW flow on line #3?
A. 500 MW
B. 400 MW
C. 1000 MW
D. 1500 MW
A. 500 MW
True or False: A Balancing Authority is obligated to operate to protect against uncontrolled separation from a single most severe contingency
A. True
B. False
A. True
Dynamic thermal ratings are ratings that limit transmission line loading
A. With current temperature and wind speed
B. Based on projected transaction schedules
C. Based on current transaction schedules
D. With a conservative mind set
A. With current temperature and wind speed
In what manner is voltage reduction typically implemented to obtain load relief?
A. Appealing to the public
B. Changing transformer taps
C. Providing a potential difference
D. Increasing amp flow
B. Changing transformer taps
There are pieces of equipment whose primary function is to adjust system MW flow. One example of this type of equipment is a
A. Tap changing transformer
B. Reactor
C. Capacitor
D. Phase shifting transformer (PST)
D. Phase shifting transformer (PST)
Total transfer capability is defined as:
A. The maximum amount of power that can be scheduled over a transfer path
B. The total actual and scheduled power that can be transferred over a transfer path minus USF.
C. The maximum amount of actual power that can be transferred over a transfer path
D. The total scheduled power, plus any unscheduled flows, which may flow over a transfer path
C. The maximum amount of actual power that can be transferred over a transfer path
If your system experiences an IROL violation, as an operator, you are supposed to return your transmission system to within its limits as soon as possible, but no longer than how many minutes?
A. 30 Minutes
B. 60 Minutes
C. 10 Minutes
D. 20 Minutes
A. 30 Minutes
Two parallel transmission lines are both rated for 480 MVA and are currently loaded at 300 MVA each. If one of the lines trip, it will cause the other line to be loaded above its rating by more than 100 MVA. What should you do if you receive notification that due to a system emergency one of the lines must come out of service?
A. Re-dispatch available generation and remove the line from service
B. Delay the outage until a nearby steam unit can be started
C. Wait until the line trips on its own
D. Take the line out of service and shed 100 MW of load
A. Re-dispatch available generation and remove the line from service
Following a contingency or other event that results in an Operating Security Limit Violation, the Balancing Authority shall return its transmission system to within Operating Security Limits as soon as possible, but no longer than
A. 20 minutes
B. 60 minutes
C. 10 minutes
D. 30 minutes
D. 30 minutes
Three transmission lines connect a generation source to a load area. Line #1 has an impedance of 30 ohms, line #2 = 40 ohms and line #3 = 60 ohms. Total power flow is initially 2000 MW. Assume that line #1 trips. Assuming no generation or load changes and neglecting power losses, what will the MW flow on line #3?
A. 1600 MW
B. 400 MW
C. 800 MW
D. 1200 MW
C. 800 MW
Computer simulations show that for a 100 MW schedule from Bus “A” to Bus “B”, 63 MW of the schedule will flow on the scheduled path and the remainder will flow on other parallel paths. What is the distribution factor for the unscheduled paths?
A. 1
B. 0
C. 0.37
D. 0.63
C. 0.37
In order for each Transmission Operator to protect its system’s voltage levels under normal and contingency conditions, they must acquire which of the following?
A. Sufficient transmission capacity
B. Sufficient reactive resources
C. Dynamic reactive resources
D. Sufficient generation supplies
C. Dynamic reactive resources