Valuations Flashcards

1
Q

What is the purpose of a valuation?

A

To provide advice to the certifier on value to allow them to issue their interim certificate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How is the Construction Act relevant with regards to valuations?

A

It contains statutory requirements relating to interval and procedure for contracts that have a duration of over 45 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What happens if a contract does not contain the valuation provisions required by the Act?

A

The Scheme for Construction Contracts will apply to fill the gaps

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the provisions of the Scheme for Construction Contracts?

A
  • Payment becomes due 7 days from the end of a relevant period (28 days)
  • The final date for payment is 17 days later
  • A notice should be issued to the contractor 5 days after payment becomes due stating the amount certifier and the basis on which it was calculated
  • If money is to withheld, a written notice must be given to the contractor no later than 7 days before the final date for payment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the standard provisions under JCT?

A
  • Interim Valuation Date is the nearest business day in the month to the date stated
  • Due dates are 7 days after interim valuation date.
  • Payment notice shall be given to contractor 5 days after the due date.
  • Final date for payment is 14 days from its due date.
  • A payless notice is to be issued no less than 5 days from final date for payment.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the main elements of a valuation?

A

a) Preliminaries
b) Measured work
c) Variations
d) Materials on site
e) Materials off site
f) Loss and expense
g) Retention

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What needs to be in place for you to include payments for materials on site?

A

The materials should be for the works, adequately protected, delivered to programme and in a reasonable quantity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What needs to be in place for you to include payments for materials off site?

A
  • Proof that ownership will transfer to the employer on payment (vesting certificate)
  • Insurance until materials arrive at site
  • Materials are clearly labelled as for the site and set apart from other materials
  • A materials off site bond has been provided if required
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a retention of title clause?

A
  • Where the sub contractor or supplier retains ownership of materials until they are paid for them by the contractor
  • This is why vesting certificates are important – otherwise the employer may pay for materials that are not owned by the contractor
  • Can lead to disputes in the event of insolvency
  • General wisdom is materials that have been incorporated in the works belong to the employer BUT less clear if they haven’t
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do you evaluate interim valuations?

A
  • Go to site and conduct valuation
  • Check work done, materials on site, materials off site
  • Value preliminaries, agreed variations and any claims
  • Valuation amount is gross valuation, less r retention, less previous payment.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the options for conducting valuations under JCT D&B?

A
  • Alternative A – stage payments

- Alternative B – periodic payments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do stage payments work?

A
  • The stages and their values are set out in the contract particulars
  • The stages are usually related to the completion of significant design items e.g. substructure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why might stage payments be chosen in the contract and used?

A

Easier to manage, no requirement for a PQS as the employer could manage. The described works are either completed or not.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When might advance payments be used?

A
  • This is dealt with under clause 4.8
  • It allows the contractor to receive lump sum payment in advance
  • The payments, values and dates should be set out in the contract particulars
  • They may be used where the contractor incurs high costs at the start of a project
  • E.g. items with long lead times or the need to purchase specialist plant for manufacturing
  • JCT provides an advance payment bond to cover the employer financially
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the disadvantages of advance payments?

A
  • May reduce the incentive of the contractor
  • Bad for the employer’s cashflow
  • Concerns over why the contractor can’t fund the expenditure – insolvency worries
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

If a contractor’s work has been certified and paid in an interim valuation, can it be devalued in a later certificate?

A
  • Payment in an interim certificate is a payment on account of the final sum
  • It is always open to the architect to certify a sum that is devalued in a later certificate