Cost Estimating/ Planning Flashcards
What types of estimate are there?
a) Budget / feasibility
b) Cost estimate
c) Cost plan
What is a feasibility estimate?
- A high level exercise to assess whether a project is financially viable and to set an outline budget for the scheme
What is the format of a feasibility / budget estimate?
- Rate per m2 or per functional unit
- May be presented as a range
What is a functional unit?
- The ‘factors which express the intended use of the building better than any other’
- E.g. number of bedrooms in a hotel, number of beds in a hospital
What information do you need to be able to carry out a feasibility estimate?
- Type of building (function)
- New build, extension or refurb
- Location
- Size
- Indication of quality
- Site visit
What is the % error on a feasibility estimate?
10%
What is a cost estimate?
A forecast of the possible cost of a building based on historical data
What are the principal components of a cost estimate?
- Construction cost
- Preliminaries
- Contractor’s OH&P
- Contingency
- Inflation
- Assumptions - programme
- Exclusions
- Area Schedule
- Basis of Estimate – drawings / specifications list
Name the main elements of an elemental estimate
- Substructure – excavation and substructure
- Superstructure – frame, upper floors, external walls, roof, internal finishes
- Services
- External works
What is usually excluded from a cost estimate?
- Professional fees
- VAT
- Client decant costs
- Loose fixtures and fittings
- Inflation
- Site acquisition costs
- Section 106s
- Removal of asbestos
Why is VAT excluded?
- Because different clients will incur different levels of VAT, might not be applicable
- We would not be in a position to know the correct rate unless informed of it
What is the % error on a cost plan?
5%
What is contingency?
A sum included in the estimate to cover unknown expenses or unmitigated risks during the project
How is contingency assessed?
- Should reflect the risks and unknowns specific to the project
- Depends on items such as status of design info, project complexity, project type (new build/refurb), type of estimate, risks identified in risk register
- Can include separate client contingency (for client changes), and project risk reserve (based on risk register items not accounted for in estimate)
- It is common to have a higher % for refurbishment work due to the higher level of unknowns and therefore risks
What are preliminaries?
- They define the scope of works
- Include the project particulars, lists of drawings, description of the site, scope of work, details of management arrangements
- Often contain items for pricing which are general items needed by the contractor to carry out the work that cannot be attributed to specific items of work
Where do you find the guidelines to prepare preliminaries?
SMM7
Name some preliminaries sections
A10 – project particulars
A54 – provisional sums
What should be considered when assessing preliminaries levels?
a) Length of contract
b) Location – accessibility, space restrictions, accommodation possibilities etc
c) Type of project – new build / refurb, tower / one story etc
d) Size of project
e) Need for temporary works
f) Need for security
g) Limitations on method and sequencing of works, working hours – supervision requirements
h) Sectional completion
i) Availability of services
j) Level of contractor’s designed works
How do you take account of inflation when benchmarking / cost estimating?
Using TPI’s (Tender Price Index)
What do TPIs show?
They reflect changes in the level of pricing contained in the lowest accepted tenders for new work to take account of market conditions – compares against base rates
Where can you get this information from?
- BCIS
- In house forecasts
How do you take account of location?
Through the application of location indices