Cost Estimating/ Planning Flashcards

1
Q

What types of estimate are there?

A

a) Budget / feasibility
b) Cost estimate
c) Cost plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a feasibility estimate?

A
  • A high level exercise to assess whether a project is financially viable and to set an outline budget for the scheme
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the format of a feasibility / budget estimate?

A
  • Rate per m2 or per functional unit

- May be presented as a range

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a functional unit?

A
  • The ‘factors which express the intended use of the building better than any other’
  • E.g. number of bedrooms in a hotel, number of beds in a hospital
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What information do you need to be able to carry out a feasibility estimate?

A
  • Type of building (function)
  • New build, extension or refurb
  • Location
  • Size
  • Indication of quality
  • Site visit
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the % error on a feasibility estimate?

A

10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a cost estimate?

A

A forecast of the possible cost of a building based on historical data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the principal components of a cost estimate?

A
  • Construction cost
  • Preliminaries
  • Contractor’s OH&P
  • Contingency
  • Inflation
  • Assumptions - programme
  • Exclusions
  • Area Schedule
  • Basis of Estimate – drawings / specifications list
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Name the main elements of an elemental estimate

A
  • Substructure – excavation and substructure
  • Superstructure – frame, upper floors, external walls, roof, internal finishes
  • Services
  • External works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is usually excluded from a cost estimate?

A
  • Professional fees
  • VAT
  • Client decant costs
  • Loose fixtures and fittings
  • Inflation
  • Site acquisition costs
  • Section 106s
  • Removal of asbestos
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Why is VAT excluded?

A
  • Because different clients will incur different levels of VAT, might not be applicable
  • We would not be in a position to know the correct rate unless informed of it
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the % error on a cost plan?

A

5%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is contingency?

A

A sum included in the estimate to cover unknown expenses or unmitigated risks during the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How is contingency assessed?

A
  • Should reflect the risks and unknowns specific to the project
  • Depends on items such as status of design info, project complexity, project type (new build/refurb), type of estimate, risks identified in risk register
  • Can include separate client contingency (for client changes), and project risk reserve (based on risk register items not accounted for in estimate)
  • It is common to have a higher % for refurbishment work due to the higher level of unknowns and therefore risks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are preliminaries?

A
  • They define the scope of works
  • Include the project particulars, lists of drawings, description of the site, scope of work, details of management arrangements
  • Often contain items for pricing which are general items needed by the contractor to carry out the work that cannot be attributed to specific items of work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Where do you find the guidelines to prepare preliminaries?

A

SMM7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Name some preliminaries sections

A

A10 – project particulars

A54 – provisional sums

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What should be considered when assessing preliminaries levels?

A

a) Length of contract
b) Location – accessibility, space restrictions, accommodation possibilities etc
c) Type of project – new build / refurb, tower / one story etc
d) Size of project
e) Need for temporary works
f) Need for security
g) Limitations on method and sequencing of works, working hours – supervision requirements
h) Sectional completion
i) Availability of services
j) Level of contractor’s designed works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

How do you take account of inflation when benchmarking / cost estimating?

A

Using TPI’s (Tender Price Index)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What do TPIs show?

A

They reflect changes in the level of pricing contained in the lowest accepted tenders for new work to take account of market conditions – compares against base rates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Where can you get this information from?

A
  • BCIS

- In house forecasts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

How do you take account of location?

A

Through the application of location indices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Why do you need to take account of location?

A
  • Different market conditions in different locations

- Different cost of materials, different wage rates etc – impact on tender levels

24
Q

What does BCIS stand for?

A

Building Cost Information Service

25
Q

What is BCIS?

A

Provides construction cost and price information through publications, online services and price books

26
Q

What is a cost plan?

A
  • Presents the estimated cost into a structural elemental or functional format
  • It shows how the design team proposes to distribute the funds available on the elements of the proposed building.
27
Q

What is the purpose of a cost plan?

A
  • It is used by the cost consultant to control the development of the design
  • It identifies the client’s agreed cost limit and how the money is to be allocated to the different parts of the building.
28
Q

What is the difference between a cost estimate and a cost plan?

A
  • Cost plan is a plan of costs for the works in preparation for turning into a cost report to check against.
  • Estimate is a forecast of construction cost
29
Q

What is buildability?

A
  • Harnessing the contractor’s expertise and knowledge during the design stage
30
Q

What are the advantages of buildability?

A
  • Better programming, sequencing and construction methods – a quicker construction time
  • Lower capital and life cycle costs
  • Improved quality in the finished building’s performance and maintenance characteristics
31
Q

What is a wall to floor ratio?

A
  • This shows the relationship between wall area and floor area
  • It is used to show the cost efficiency of the building
  • The lower the ratio the cheaper the building as there is less external wall area per m2 of floor area
32
Q

What is the most efficient shape?

A
  • A circle
  • BUT this is not the most efficient shape as it has a poor lettable floor area – difficult to fit out
  • THEREFORE a square is the best
33
Q

What is the difference between cost and price?

A
  • Cost is the total of labour, plant, materials and management deployed for a specific activity
  • Price is the amount a purchaser / client will pay for an item or product – it is cost plus profit
34
Q

How would you prepare an estimate for M&E works?

A
  • I would ask an M&E specialist surveyor to undertake the estimate
  • For feasibility estimates the M&E amount would be included in the m2/functional unit rate
35
Q

What is GEA?

A
  • Gross External Area

- This is the area of the building measured externally at each floor level

36
Q

What is GIA?

A
  • Gross Internal Area
  • This is the area of the building measured to the internal face of the perimeter wall at each floor level
  • Excludes external open sided balconies, fire escapes, canopies, external walls, fuel stores
37
Q

What is NIA?

A
  • Net Internal Area
  • This is the area of usable space measured to the internal face of the perimeter wall at each floor level
  • Excludes internal structural walls and columns, spaces with headroom less than 1.5m, corridors and circulation space used in common, permanent lift lobbies, toilets, cleaners cupboards, plant rooms
38
Q

Where are all of these defined?

A
  • The Code of Measuring Practice, 6th Edition, published by the RICS
39
Q

What is the purpose of the Code of Measuring Practice?

A
  • Provides precise definitions to permit the accurate and consistent measurement of buildings
40
Q

What would you expect the percentage of NIA to GIA / GEA to be?

A
  • It depends on the type of project being undertaken (school, hospital, office etc…)
  • If it were an office build I would expect the NIA to GIA to be in the region of 70-85%, where 70% is not good and 85% is excellent.
41
Q

Where do you get cost information from?

A

a) In house historic data
b) Benchmarks
c) BCIS
d) Building cost models
e) SPONS and other price books (Laxtons etc)
f) Sub contractors and suppliers

42
Q

What do you measure in accordance with?

A

SMM7

43
Q

What does SMM7 stand for?

A

Standard Methods of Measurement, 7th edition

44
Q

What does SMM7 do?

A
  • SMM7 identifies the unit to which the work is measured and the requirements of measuring the works.
  • SMM7 is authorised by agreement between the Royal Institution of Chartered Surveyors and the Construction Confederation.
45
Q

How do you measure brickwork walls under SMM7 – and what other items would you measure in association?

A

Under SMM7 brickwork walls are measured in m2. Other items to measure in association with brickwork include:
Isolated piers, Isolated casings, Chimney stacks, Projections, Arches, Brick reinforcement, Sundry items, Forming cavity, Closing cavities

46
Q

What is a Section 106 agreement?

A
  • From Town and Country Planning Act 1990 section 106 (hence name)
  • They are also referred to as planning obligations
  • They are typically agreements between local authorities and developers negotiated in the context of granting planning consent
47
Q

What does a Section 106 Agreement need to be?

A
  • relevant to planning
  • necessary to make the proposed development acceptable in planning terms
  • directly related to the proposed development
  • fairly and reasonably related in scale and kind to the proposed development
  • reasonable in all other respects.
48
Q

What sort of things is the money spent on?

A
  • Affordable housing
  • New open space or environmental improvements
  • New roads and transport capacity
  • Health and education facilities
49
Q

What is construction to ‘shell and core’?

A
  • The basic structure, services and envelope of the building
  • AND the fit out of landlord / common areas
  • E.g. reception, toilets, lifts, cores, base services are terminated at breakout points to floors, life safety services infrastructure
50
Q

What is a CAT A fit out?

A
  • Also known as a ‘developer’s fit out’
  • Provides the generic requirements to suit most developers
  • E.g. life safety elements and basic fittings - suspended ceiling tiles, raised floors, carpet, lighting, power distributed to floor plates
51
Q

What is a CAT B fit out?

A
  • Overlays the CAT A provision with bespoke elements particular to the needs of the building user to enable the tenant to occupy and use the space
  • E.g. partitions, power distributed to floor boxes, data cabling, artwork and branding, upgrading CAT A finishes and toilet finishes etc
52
Q

Where could you find the definitions for CAT A & B fit outs?

A
  • British Council of Offices (BCO) fit out guide
53
Q

What is BWIC?

A
  • BWIC stands for Builders Work In Connection and is usually set as a percentage of the services cost.
  • Depending on the size of the job and complexity will determine the percentage of BWIC.
  • BWIC accounts for any drilling, fixing, cutting etc… that the builders do whilst undertaking the services.
  • BWIC can be measured in accordance with SMM7 when doing a BOQ’s.
54
Q

How would you create a cashflow forecast?

A
  • Need to know the construction programme and contract value
  • Then would use a Cashflow computer programme
  • Or by attributing costs to a construction programme.
  • Split works into packages as shown on contract programme and include individual s-curves for each package.
55
Q

What’s the benefit of cashflow forecast?

A
  • Allows employer to gain an understanding of financial requirements over the duration of the project duration.
  • Also acts as a check against valuations – early indication of financial difficulties
56
Q

What would you include in a financial report (CVR)?

A

a) Contract sum
b) Instructed variations
c) Potential future variations as advanced warnings
d) Claims
e) Anticipated final account total
f) Total of certified payments

57
Q

What is the purpose of a financial report?

A
  • To report against budgeted values and act as a working cost check on the project budget.
  • To give the Client an understanding of any savings or additional monies required.
  • To report on contract progress against pre-contract predictions.