Completion and Certificates Flashcards

1
Q

What is the date for completion?

A

The date fixed and stated in the contract particulars

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How does the ‘date for completion’ differ from the completion date?

A

Completion date is the date when the works are complete taking into account changes (like EOT) and is subsequently fixed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does it mean when ‘time is at large’?

A
  • There is no fixed completion date

- The contractor must only complete the works in a reasonable time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is practical completion?

A

When the employer takes back possession of the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is sectional completion?

A

The completion and handover of the works to the employer in agreed stages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Do the works have to be totally completed before practical / sectional completion is achieved?

A
  • Practical completion is a vague concept
  • It is not defined in JCT
  • It is reliant on the employer’s agents opinion that the works are complete
  • It should not be conditional
  • It is common practice for PC to be granted when the works are substantially complete – i.e. there may be minor defects or omissions BUT nothing that would prevent the employer taking occupation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the recourse if the contractor disagrees with the employers agent that the works are not completed?

A

Adjudication

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the consequences of practical / sectional completion?

A
  • Half of the retention is released
  • The Rectification Period begins
  • The contractor’s responsibility for insuring the works (if applicable) ends
  • The contractor’s liability for liquidated damages ends
  • The employer is now responsible for any damages to the works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is partial possession?

A

Where the employer requests and the contractor consents to the employer taking possession of the works / part of the works before the date for practical / sectional completion?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the difference between partial possession and sectional completion?

A

Sectional completion is a contractual obligation to hand over the section at the stated date, partial possession relies on the contractor’s consent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does the employers agent have to do at partial possession?

A

Issue to a written statement to the contractor showing the relevant part and stating relevant date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the consequences of partial possession?

A
  • For the relevant part practical completion is deemed to have occurred on the relevant date
  • Therefore the same consequences follow
  • In addition, the liquidated damages for the works / that section are reduced by the proportion that the value of the relevant part relates to the contract / section sum
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the rectification period?

A

The contractor has an obligation to make good any defects, shrinkages or other faults that arise during this period of time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How long is the defects rectification period?

A

Six or 12 months, normally 12 months to see all the seasons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How can the employers agent get the contractor to fix the defects that arise during this period?

A

No later than 14 days after the end of the Rectification Period the architect must issue a written statement to the contractor detailed all of the defects that have arisen and need to be made good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly