Unit 2 Flashcards

1
Q

Why would plumb lines need to be pulled?

A

When the survey indicates that the hoistway is out of plumb

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How many workers are permitted to tie off to a single life line?

A

One

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the main reason for surveying the hoistway prior to rail installation?

A

To ensure elevator will fit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What drawing should be used to reference dimensions with the general contractor

A

Final layout

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Determine the dimensions of the clear hoistway on diagram provided?

A

6’7” x 7’4”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What must be installed in the hoistway to protect workers from falling debris?

A

Overhead protection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What would be considered adequate overhead protection?

A

Fully screen hoistway openings and holes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are most elevator hoistway components measured from when installing in the hoistway?

A

Main guide rail location

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the minimum number of plumb lines required to take hoistway measurements?

A

2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What reference point must be used when installing hoistway door frames?

A

Building grid lines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly