Unit 2 Flashcards
Rule 1
SLOC function point equivalence.
1FP= 125 SLOC for procedural language, 300 SLOC for assembly language and ,<20 SLOC for some oop languages.
Rule 2
Project Duration Estimation
Function points raised to the power 0.4 predicts the approximate number of development time in calendar month
Rule 3
Rate of requirement creeps
User requirements creeps at an average rate of 2% per month from design to coding phase
Rule 4
Defect removal Efficiency
Each software review, inspection and test steps will find and remove 30% of bugs that are present.
Rule 5
The size of software (in FP) divided by 150 predicts the approximate number of personnel required for developing the application.
Software development effort estimation
App no of staff months of effort to develop a software = software development time * no of personnel required.
Rule 7
Function points
FP/500 predicts the approximate number of personnel required for regular maintenance activitiy