Traditional Procurement Flashcards

1
Q

What is traditional procurement?

A
  • Traditional procurement involves separating design from construction.
  • The employer first appoints consultants to design the project in detail.
  • A contractor is then appointed to construct what the designers have specified.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the characteristics of traditional procurement?

A
  • The contractors tender is based on a complete design produced by the employers consultants.
  • Assuming no significant design changes arise, construction costs can be determines with reasonable certainty before work begins.
  • The employer retains the design consultants during construction. The consultants prepare any additional design information and review CDP designs prepared by the contractor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the advantages of traditional procurement?

A
  • The employer retains control of the design.
  • The design is largely finalised before the contractors tender for the build, this means the employer knows exactly what they are getting.
  • All tenders produce a submission based on the same information (tender returns are easier to compare).
  • Assuming the design is robust, reasonable price certainty is achieved at contract award.
  • There is minimal built-in risk premium as employer assumes design risk.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the disadvantages of traditional procurement?

A
  • The overall project duration is often longer than other procurement methods as there is limited opportunity to overlap design and construction phases.
  • Limited opportunity for contractor buildability input.
  • Design risk is retained by the employer, any changes post contract will be a variation.
  • Dual point of responsibility (employer for design and contractor for construction).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When might traditional procurement be appropriate?

A
  • When the employer has specific or detailed design requirements.
  • When cost certainty is important.
  • When the shortest overall programme is not the employers main priority.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly