Design & Build Procurement Flashcards
1
Q
What is Design & Build procurement?
A
- Where the contractor is responsible for completing the design and executing the construction work phase of the project.
2
Q
What are the key characteristics of Design & Build?
A
- Under JCT, the employers team produces a set of employers requirements, the contractor then responds to the ER’s with their proposals.
- The original employers design team may be novated to the contractor for continuity, or the contractor may appoint their own design team
- The contractor is responsible for the design, planning, organisation, control and construction of the works.
- Design risk is transferred to the contractor.
3
Q
What are the advantages of design & build?
A
- Single point responsibility for design and construction (contractor).
- Earlier commencement on site is possible if design and construction can be overlapped (reduced project duration).
- Benefit of contractors expertise during design stage (buildability input).
- Design and construction risk rests with the contractor.
- Provides more cost certainty than traditional procurement.
4
Q
What are the disadvantages of design & build?
A
- The design is only as good as the employers requirements (the employer may find it difficult to prepare a sufficiently comprehensive brief).
- More complex to compare tender sums.
- Employer changes can be difficult to value and expensive.
- The employer may have less control over aesthetics and quality.
- The contractor will build in risk premiums into their tender.
5
Q
When might design & build be appropriate?
A
- Where there is a need to make an early start on site.
- Where the employer wishes to minimise their risk profile.
- For technically complex projects where the design will benefit from the contractors buildability input.
- Where retaining control of the design is not a priority.
6
Q
What additional insurances might be needed under a design & build contract?
A
- The contractor and their design team will have design responsibility; therefore, it is likely that additional professional indemnity insurance will be required.
7
Q
What are employers requirements (ER’s)?
A
- A set of documents produced by the employer to inform the design and construction of the project.
- Documents typically include performance specs, drawings, initial designs etc.
8
Q
What are the contractors proposals (CP’s)?
A
- CPs are prepared by the contractor which responds to the employers requirements.
- In this document, the contractor will set out a more detailed design (based on the employers requirements), which will require further development throughout the course of the project.
9
Q
What procurement route poses the least risk to the employer?
A
- Design & build because the design risk is transferred to the contractor.
10
Q
Why does the employer usually pay a premium for design & build procurement at tender stage?
A
- The contractor will usually factor in an allowance within their tender return in exchange for taking on the design risk.
11
Q
Under design & build, who executes the design for the contractor?
A
- The contractor may use their own in-house designers or they can appoint external consultants.
- The employers original design team can also be novated to the contractor.