Construction Management Procurement Flashcards

1
Q

What is construction management procurement?

A
  • The employer directly appoints multiple trade contractors instead of a single main contractor.
  • The employer places individual contacts with the trade contractors themselves.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the key characteristics of construction management?

A
  • The employer places a direct contract with each trade contractor and utilises the expertise of a construction manager to coordinate the works.
  • The construction manager programmes and coordinates the works.
  • The construction manager has no direct link with the trade contractors.
  • The construction manager has no vested interest in the financial outcome of the project and, barring professional negligence, carries no risk.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key advantages of construction management?

A
  • Quick start on site.
  • Overall project duration reduced by overlapping the design and construction.
  • The construction manager can contribute to the design and project planning processes.
  • Changes in design can be accommodated without paying a premium.
  • Can be cost benefits due to the placing contracts direct with the trade contractors.
  • The employer has means of redress with trade contractors through direct contractual link.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the disadvantages of construction management?

A
  • Price certainty not achieved until the last trade package is let.
  • The procurement route requires an informed, experienced and proactive employer to work.
  • The employer has a lot of consultants and trade contractors to manage.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When might construction management be appropriate?

A
  • The employer is experienced in construction and has the suitable resources to manage the project.
  • The employer wants to achieve an early start on site.
  • The employer wants the flexibility to make minor changes to the design/specification through the process with minimal impact on cost and time.
  • The project is technically complex and requires detailed engagement of specialist consultants and trade contractors.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which is the riskiest procurement route for the employer?

A
  • Construction management as the employer places individual contracts direct with each trade contractor and the construction manager carries no risk (barring professional negligence).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly