Tender Returns & Analysis Flashcards

1
Q

What is a form of tender?

A
  • A document that the contractor signs and returns with their tender submission stating their price and programme.
  • Formal acknowledgement that the contractor understands and accepts the terms and conditions of the tender docs.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What information is typically included in the form of tender?

A
  • Tender sum
  • Date until which the price remains valid.
  • Construction period
  • Confirmation of the tender being boba fide.
  • Tenderer details and signature.
  • Acceptance of terms and conditions.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When seeking tenders for construction work, in addition to the actual price for the work, what additional information might be requested?

A

Qualitative submission including:
- Demonstration of previous experience.
- Proposed team and hierarchy.
- Proposed methodology.
- References.
- Programme.
- H&S information.
- VE proposals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Once tenders have been submitted, what should be examined for compliance with the ITT?

A
  • Arithmetical errors.
  • Pricing errors (items not priced).
  • Pricing methods (front loading).
  • Ensure contractors proposals against employers requirements.
  • Check form of tender is complete and signed.
  • Qualifications and exclusions.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What happens if a tender is submitted late?

A

Public sector: tender should NOT be accepted.
Private sector: at the discretion of the employer. Advise that the safest option is not to consider as risk of collusion, bid-rigging.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Would you open a late tender submission for a school project?

A
  • The tender should not be considered on the basis that the project is funded by the public sector.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the danger of accepting a very low tender submission?

A
  • Contractor may try to recover their costs with variations and/or claims.
  • May be an indication that the contractor is in poor financial standing or cash flow position.
  • Elements of the project might not be priced accurately (potential for adversarial relationship to develop post contract).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How do you deal with qualifications within the tender submission?

A
  • The employers team should look to resolve the qualifications prior to tender award.
  • Procedures associated with qualifications should be outlined in the tender instructions.
  • If the qualifications are unauthorised it might invalidate the tender leading to qualification.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How would you deal with errors identified in the tender submissions?

A
  • The JCT Tendering Practice Note suggests two options to deal with errors.

Alternative 1: Confirm or withdraw
Alternative 2: Confirm or amend

  • I would identify which option has been drafted into the tender pack and act accordingly.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What would you do if you considered a contractor submitting the lowest tender to be in financial difficulty?

A
  • Company accounts will be reviewed as part of the tender evaluation process.
  • Consider a performance bond. If contractor fell insolvent, employer could call on the bond and appoint another contractor to complete the project.
  • Consider a parent company guarantee.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

On what grounds would you advise the client to retender?

A
  • Not enough tender returns.
  • The tendering procedure is compromised.
  • Significant design, methodology or programme changes after issuing the tender documents.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How would you deal with a front-loaded tender?

A
  • Request contractor removes front loading. If the contractor refuses, this may be grounds for disqualification.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How could you reduce the risk of contractors pulling out during the tender process?

A
  • Ensure the tender information is as accurate as possible.
  • Ensure the tender period is long enough (extend if required).
  • Check the contractors have the capacity to tender.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a contract sum analysis under design & build procurement?

A
  • A CSA is an alternative pricing document to a schedule of works or BOQ.
  • It’s often prepared in a standard format by the employers team to support the tender analysis.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What information is typically included in a tender analysis report?

A
  • List of tenders received.
  • Original tender sums.
  • Any qualifications identified.
  • Post-tender adjustments.
  • Revised tender sun.
  • Issues to be resolved.
  • Comparison if tender returns.
  • Comparison of Pre-Tender estimate.
  • Recommendation.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

If the tender was received on time, but the works were delayed and did not commence until a few months later, what would you need to check?

A
  • Form if tender to see how long the price was valid for.
17
Q

If the contractor (in their tender return) put a cost against an item and marked it as provisional, what would you do?

A
  • I would seek further information from the contractor and request that this be removed/firmed up.
  • Subject to the tender instructions, this may invalidate the tender.
18
Q

If you think the delivery programme is tight, how can you give comfort to the contractor regarding liquidated damages (to avoid them excessively pricing in their tender sum)?

A
  • The contract can be amended to include an LD free period.
19
Q

If you think the delivery programme is tight, how can you give comfort to the contractor regarding liquidated damages (to avoid them excessively pricing in their tender sum)?

A
  • The contract can be amended to include an LD free period.
20
Q

What is the purpose of a pre-tender estimate?

A
  • A PTE is the last and most accurate cost check of the project before it is issued to tender.
  • The estimate is then used to compare against tender submissions.
21
Q

What happens if the tender prices are higher than the pre-tender estimate?

A
  • Review tender analysis against PTE to identify major differences in price.
  • Look at external factors have affected tenders.
  • Undertake value engineering to bring project to within budget.