Time Management SOP Flashcards

1
Q

Having an accurate schedule at the beginning of a project and ongoing schedule maintenance helps to: (All the above)

A
  • Avoid claims
  • Deliver the project on time
  • Provide a solid basis for quantifying time impact
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The CPM schedule can be used as a tool to resolve disputes. T/F

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What CPM Scheduling graphical format is most often used with today’s computer software?

A

Precedence Diagram Method (PDM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The essential elements of a CPM schedule are:

A

Activities, durations, logical relationships, and constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

An activity’s duration can be based on: (All the above)

A
  • Rate of work
  • Professional judgment
  • Experience
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A project schedule shows that a sub-contractor can start painting the exterior of a building after the stucco has been finished. What type of activity relationship is this an example of?

A

Finish to Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

An activity that must be completed by a certain date will have this type of date constraint in the schedule.

A

Finish no later than

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How is a CPM schedule different from the traditional bar or Gantt chart?

A

The CPM schedule shows logical relationships between activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The overuse of constraints in a CPM schedule can diminish its overall value. T/F

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which term means the number of days that an activity can be delayed without delaying the end date of the project?

A

Total Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which term means the amount of time an activity can slip without impacting the early start of its successor?

A

Free Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The “Critical Path” is the longest sequence of activities that controls the completion of the project. T/F

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A concept schedule should be developed in the Pre-Design phase. T/F

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Factors that should be considered when developing a concept schedule include the owner’s objectives, funding sources, contract type, site location, and government regulations. T/F

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

During the Procurement phase, it is important to develop language for the construction specifications related to the schedule requirements. T/F

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

During Post-Construction, a(n) ________ schedule should be developed that contains all actual start and finish dates.

A

As-Built

17
Q

A good construction schedule is detailed, complete, realistic, reasonable, detailed, and manageable; and has consideration for specialty work and sufficient time to complete work. T/F

A

True

18
Q

Time Impact Analysis is a procedure that helps to:

2 Answers

A
  • Substantiate equitable time adjustment of contractual terms
  • Document unplanned delays that were not the GC’s responsibility
19
Q

The contractor is automatically entitled to additional compensation if it is determined he/she is awarded an equitable time extension. T/F

A

False

20
Q

The stucco needs to dry for a week before the painter can start painting the exterior. What type of activity relationship is this an example of?

A

Finish to Start with Lag