Time Management (6) Flashcards

1
Q

Estimation types

A
  • one-point estimating
  • analogous estimating
  • parametric estimating
  • three-point estimating (PERT analysis, Program Evaluation and Review Technique)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EAD

A

Expected Activity Duration or PERT (P + 4M + O)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

SD

A

Activity Standard Deviation (P - O)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

AV

A

Activity Variance [(P - O)/6]^2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Project Expected Duration or PERT

A

sum of critical path EADs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Project Variance

A

sum of critical path AVs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Project Standard Deviation

A

square root of Project Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Range of the Estimate

A

Expected Duration or Pert +/- Standard Deviation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

types of reserves

A
  • contingency reserves

- management reserves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Schedule Network Analysis

A

used to create the final schedule once the initial one is ready

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Schedule Network Analysis techniques

A
  • Critical path method
  • Schedule compression
  • What-if scenario analysis
  • Resource leveling
  • Critical chain method
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

difference between schedule and a time estimate

A

schedule is calendar-based

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

total float (slack)

A

the amount of time activity can be delayed without delaying project end date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

free float (slack)

A

the amount of time activity can be delayed without delaying next the early start of its successor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

project float (slack)

A

the amount of time project can be delayed without delaying the externally imposed project completion end date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

negative float (slack) means

A

you are behind

17
Q

schedule compression methods (and impacts)

A
  • fast tracking (increased risk)
  • crashing (increased cost)
  • reducing scope (decreased customer satisfaction)
  • moving more experienced people to activities on critical path (increased risk)
  • cut quality (decreased customer satisfaction, increased risk)
18
Q

what-if scenario analysis

A

changing assumptions and seeing how they affect the project (e.g. through Monte Carlo Analysis)

19
Q

Monte Carlo simulation results

A
  • probability of completing the project on any specific day
  • the probability of completing the project for any specific amount of cost
  • the probability of any activity actually being on the critical path
  • the overall project risk
20
Q

Resource leveling

A

lenghtens the schedule and increases cost in order to deal with a limited amount of resources

21
Q

Project Schedule formats

A
  • network diagram (showing interdependencies)
  • bar chart (team reporting, tracking progress)
  • milestone chart (senior management reporting)
22
Q

Methods to draw network diagrams

A
  • Precedence Diagramming Method (PDM) or Activity on Node (AON)
  • Graphical Evaluation and Review Technique (GERT)
23
Q

Milestones are defined in

A

Define Activities process along with acitivities

24
Q

rolling wave planning

A

when project has too many unknown components (high level planning and then refining during the works where it becomes clearer)

25
Q

RBS

A

Resource Breakdown Structure - output of Estimate Activity Resources in Time Management KA. It shows the resources to be used, organized by their category and type in hierarchical image.

26
Q

potential need for additional time or funds should be addressed with ___ instead of ___

A

reserves through the risk management process instead of padding

27
Q

types of dependencies

A
  • discretionary dependency
  • mandatory dependency
  • external dependency
28
Q

heuristic is

A

rule of thumb (used consistently!), e.g. 80/20

29
Q

analogous estimating

A

top-down, high-level estimates, used for briefly estimating project costs (for management info)

30
Q

parametric estimating

A

based on variables and relationships from historical records, standard metrics and other. More detailed than analogous

two types: regression analysis/scatter diagram, learning curve,