Cost Management (7) Flashcards
1
Q
CV
A
Cost Variance EV - AC
2
Q
SV
A
Schedule Variance EV - PV
3
Q
CPI
A
Cost Performance Index EV/AV
4
Q
SPI
A
Schedule Performance Index EV/PV
5
Q
EAC
A
Estimate at Completion AC + bottom-up ETC BAC/CPI AC + (BAC - EV) AC + (BAC - EV)/(SPI * CPI)
6
Q
TCPI
A
To Complete Performance Index
BAC - EV) / (BAC - AC
7
Q
ETC
A
Estimate To Complete EAC - AC or reestimate
8
Q
VAC
A
Variance at Completion BAC - EAC
9
Q
types of cost
A
variable, fixed, direct, indirect
10
Q
accuracy of estimates - rough order of magnitude estimate
A
+/- 50%
11
Q
accuracy of estimates - budget estimate
A
-10 to +25%
12
Q
accuracy of estimates - definitive budget
A
+/- 10%