Time Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

What is the process of Time Management?

A
Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
Develop Schedule
Control Schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

In which process is the schedule management plan created?

A

The schedule management plan is creaed in integration managbement, as part of the Develop Project Management Plan process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key outputs of the Define Activities Process?

A

Activity List
Activity Attributes
Milestone List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are key outputs of the Sequence Activities process?

A

Network Diagrams

Project doc updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are key outputs of the Estimate Activity Resources process?

A

Activity resource requirements

Resource Breakdown Structure (RBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the key ouputs of the Estimate Activity Durations process?

A

Acitivy duration estimates

Project doc updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the develop schedule process? What are its key outputs?

A

The actions and tools necessary to create a bought into, approved, realistic, and formal project schedule. Outputs:

Project Schedule
Schedule baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the key outputs of the Control Schedule process?

A

Work performance measurements

change requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are mandatory and discretionary dependancies?

A

Mandatory: One Activity MUST be done after or before another; may also be called hard logic.

Discretionary: When you PREFER activities to be accomplished in a certain order; may also be called preferred, preferential, or soft logic.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are external dependancies?

A

Dependancies based on the needs of a party OUTSIDE the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a resource breakdown structure?

A

An organizational chart or table showing IDed resources by catagory.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is critical path? How does it help the project?

A

The longest path through the network diagram.

It shows the PM the shortest time in which the project can be completed.

It shows the PM where to focus his or her time.

It is used in compressing or adjusting the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is near-critical path?

A

The path closest in legnth to the critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Define lag

A

Waiting time inserted into the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Define total float and the formula for total float?

A

The amount of time an activity can be delayed without delaying the project.

Formula:
Late start - Early start
OR
Late finish - Early finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Define free float and project float.

A

Free float: The amount of time an activity can be delayed without delaying the early start date of its successor.

Project float: The amount of time the project cna be delayed without affecting the projects required end date; the desired project end date minus the actual end date.

17
Q

What are the methods to compress a schedule?

A

Crashing

Fast Tracking

18
Q

What is crashing?

A

Schedule compression through analyzing cost and schedule trade-offs to obtain the greatest compression for the least cost while maintaining scope.

19
Q

What is fast tracking?

A

Schedule compression by doing more critical path activities in parallell.

20
Q

What is the critical chain method?

A

A scheudle netowkr analysis tool that makes use of buffers.

21
Q

What is reestimating?

A

Estimating the project again after planning to make sure you can still meet the end date, budget, or other objectives.

22
Q

What is resource leveling?

A

Keeping the amount of resources used for each time period constant, thus affecting the project duration?

23
Q

What is schedule baseline?

A

the approved schedule with any approved changes, used to measure project schedule perfomrance.

24
Q

What are the main tools for displaying a schedule?

A

Netowork Diagrams, Bar Charts, Milestone Charts.

25
Q

What do network diagrams show?

A

Interdependancies between activities. How project activities will flow from beginnign to end. Netowrk diagrams may also be used to determine the critical path.

26
Q

What do simple bar charts show?

A

Project schedule or project status

27
Q

What do milestone charts show?

A

High-level project status

28
Q

What is Monte Carlo analysis?

A

A schedule netowrk analysist technique. It is used to stimulate the project to determine how likely you are to get to the project completed by any specific date or for any specific cost. It is also used in the Perform Quantitative Risk Analysis process to determine overall level of risk on the project.

29
Q

What are the following rules?

50/50 rule
20/80 rule
0/100 rule

A

Methods of progress reporting.

50 percent (or 20 percent or 0 percent) of the effort is reported complete when an activity beings.

the balance (50 percent, 80 percent, or 100 percent) is recorded only when an activity is finished.