Time Flashcards
What is the process of Time Management?
Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule
In which process is the schedule management plan created?
The schedule management plan is creaed in integration managbement, as part of the Develop Project Management Plan process.
What are the key outputs of the Define Activities Process?
Activity List
Activity Attributes
Milestone List
What are key outputs of the Sequence Activities process?
Network Diagrams
Project doc updates
What are key outputs of the Estimate Activity Resources process?
Activity resource requirements
Resource Breakdown Structure (RBS)
What are the key ouputs of the Estimate Activity Durations process?
Acitivy duration estimates
Project doc updates
What is the develop schedule process? What are its key outputs?
The actions and tools necessary to create a bought into, approved, realistic, and formal project schedule. Outputs:
Project Schedule
Schedule baseline
What are the key outputs of the Control Schedule process?
Work performance measurements
change requests
What are mandatory and discretionary dependancies?
Mandatory: One Activity MUST be done after or before another; may also be called hard logic.
Discretionary: When you PREFER activities to be accomplished in a certain order; may also be called preferred, preferential, or soft logic.
What are external dependancies?
Dependancies based on the needs of a party OUTSIDE the project.
What is a resource breakdown structure?
An organizational chart or table showing IDed resources by catagory.
What is critical path? How does it help the project?
The longest path through the network diagram.
It shows the PM the shortest time in which the project can be completed.
It shows the PM where to focus his or her time.
It is used in compressing or adjusting the schedule.
What is near-critical path?
The path closest in legnth to the critical path
Define lag
Waiting time inserted into the schedule.
Define total float and the formula for total float?
The amount of time an activity can be delayed without delaying the project.
Formula:
Late start - Early start
OR
Late finish - Early finish