Time Flashcards
What is a schedule management plan?
- how schedule will be defined
- how activity definition will be done
- how it will be measured
- how and how often the team will track progress
- what will happen if the project veers from the plan
For what 5 processes is the activity list an input?
- Sequence Activities
- Estimate Activity Resources
- Estimate Activity Durations
- Develop Schedule
- Control Schedule
When is Define Activities performed?
- After the scope is baselined
* IOW: after the requirements documentation, project scope statement, WBS, and WBS dictionary under control
What are the components of the scope baseline?
- approved scope statement
- WBS
- WBS dictionary
Exactly when are baselines created relative to the Planning and Executing process groups? IOW relative to approval of PMP?
• find out
What is rolling-wave planning and when would it be appropriate to use?
• contrast IT system creation vs. construction (waterfall?)
What are some differences between a work package & a schedule activity?
- work packages are deliverables-based, focusing on the scope of the project, while activities are focused on the work that needs to be done to execute the work packages
- WBS belongs to scope baseline, while activity list is more closely related to the schedule
- activities are verbs; work packages may be noun/verb
- each activity maps back to one and only one work package
What is an activity attribute?
additional info/parameters about an activity
What are some typical milestones?
- imposed dates (constraints)
- projected dates (based on historical info)
- phase gates
- completion of interim deliverables
- hand-offs
What is a network diagram?
- preferred method of representing activities, dependencies, and sequences
- activities drawn in order they must be performed, and the amount of time each activity takes is represented by numbers
In what process are network diagrams created?
Sequence Activities
synonym for precedence diagramming method?
activity on node
What is the relationship between activities and milestones?
activities often must be arranged so as to meet imposed milestones
Describe the ITTO for Sequence Activities?
Inputs: • Schedule Management Plan • activity list • milestone list • scope statement Tools: • PDM • dependency determination • leads & lags (waiting) Output: • schedule network diagrams
What are the 3 main classes of dependencies?
- mandatory (hard logic)
- discretionary (soft logic)
- external (must be considered, but outside scope/control; i.e. supplier)
What are the 4 types of dependencies?
Give an example of each?
- FS, SS, FF, SF
- FS: hard logic (concrete)
- SS:
- FF:
- SF:
Why must leads be clearly explained and documented?
Need a good reason not to start an activity
What 3 factors typically affect an activity’s duration?
- level of effort required
- number of resources required
- resource availability
Describe the ITTO for Estimate Activity Resources?
Inputs: • Schedule Management Plan • activity list • resource calendars • risk register • activity cost estimates (if available) Tools: • expert judgment • alternative analysis • published estimating data • bottom-up estimating Outputs: • activity resource requirements • RBS • document updates
Explain why activity duration is different than the level of effort required?
LOE is invariant, but duration is a function of: how many, who, when
When is Estimate Activity Durations performed relative to adjacent processes?
> Estimate Activity Resources
Explain the similarities and differences between crashing and fast-tracking?
Both get project done faster:
• crashing adds resources (and cost)
• fast-tracking does tasks in parallel (adds risk as discretionary dependencies (soft logic) are ignored and more is going on simultaneously)
Describe the ITTO for Control Schedule?
fill this in
Why are network paths important?
- they illustrate different sets of sequences in which activities must be performed
- they are used to identify areas of high risk
• critical path calculations show where most schedule risk exists