Cost Flashcards

1
Q

What is lifecycle costing?

A

Total cost, not just project cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is cost risk?

A

relative risk of contract for buyer and seller

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is discounted cash flow?

A

evaluate investment by estimating future cash flows and discounting them to current value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a heuristic?

A

Generally accepted rule like 80/20.

Results of parametric estimating can become heuristics.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Three-point estimating: Know formulas for beta and triangular distributions

A

tri: P+M+O / 3
beta: P+4M+O / 6
beta std dev: P-O / 6

greater std dev = greater risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

In which two KAs does three-point estimating work?

A

Time and cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the difference between estimate padding and performing contingency reserve analysis?

A

Former is a guess, latter is calculated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Differentiate among ROM estimate, budget estimate, & definitive estimate?

A

ROM - initiating -25 75%
BE - planning -10 25%
DE - execution -5 10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How are risks considered when budgeting?

A

PM MUST perform risk mgmt activities & include reserve analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is cost aggregation?

A
  • Summing bottom-up estimates

* activity-work pkg-control acct-project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are funding limit reconciliation and cost-constraint reconciliation? In what KA are they?

A
  • FLR - check cash flows
  • CCR - if planning estimate exceeds charter constraints, PM must meet w/ sponsors to explain/get approval.

• Integration Mgmt

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what is value analysis (value engineering)?

A

How can we decrease cost with same scope?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly