Theme: progress Flashcards
The purpose of the progress theme is…
to establish mechanisms to monitor and compare actual achievements against those planned in order to provide a forecast for the project objectives, including its continued viability and control any unacceptable deviations
Progress ensures that for each level of the project management team the level above can…
- monitor progress
- compare achievements with plan
- review plans & options against future situations
- detect problems
- identify risks
- initiate corrective action
- authorize future work
Time-driven controls
Checkpoint report
Highlight report
Event-driven controls
Exception report
End-stage report
Project Board controls
Authorizations: - initiation - project - stage - closure Highlight reports Exception report Issue reports Exception assessments
Project Manager controls
Authorizations: work packaged
Progress updates: checkpoint report
Exception/Changes: daily log, issue register, product status account, quality register, risk register
Min. requirements (rules + document)
P2 must:
- Define its approach to controlling progress in PID
- Be managed in stages
- Set tolerances and be managed by exception against those tolerances
- Review the business justification when exceptions are raised
- Learn lessons
Document: PID
Control in the project is provided by
Delegating authority downwards
Divide the project into management stages
Raising exceptions
Time-driven and event-driven progress reporting
Match tolerance to the document: Time, cost, scope Risk Quality Benefit
Match tolerance to the document:
- Time, cost, scope - Project plan, Stage plan, Work package
- Risk - Risk management approach, stage plan, work package
- Quality - project product description, product descriptions
- Benefit - business case