⭐️ Testing and Modeling Flashcards

1
Q

An excellent reference reliability prediction of electronic equipment is ..,.

A

MIL-HDBK-217

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

To determine whether failures observed in the test reflect actual use failures are the result of high test stresses,
what must be known?

A

The mechanism of the failures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A component fails on the average of once every 4 years
with 75% of the failures observed to occur during stormy weather,
what are the failure rates for stormy and good weather respectively?

A

Apporportion the two failure rates.

a) actual failure in 4 yr
b) actual time in 4 Yr
c) lambda (stormy ; fair)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

ESS (Environmental stress screening) is best performed at which stage of the product life-cycle?

A

Production/Manufacturing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

-

A

-

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

In Order to determine failure rates of a newly introduced high quality product,
Which method would produce the best short term result?

A

Accelerated test result

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Top-down testing requires which of the followig conditions?

A

At least one calling module must have been tested previously.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A highly accelerated stress screening (HASS) test can help to detect and seperate units with manufacuring defects
HASS test limits are typically developed from:

A

Highly accelerated life tests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

-

A

-

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Redundant components are used because:

A

Reliability of parallel components is higher

than the highest reliability component in parallel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A System consist of 4 parallel units each having a reliability of 0.8.
The system can still complete its mission with only 2 units funcioning.

If the failure rate is constant and failures are independent then the system reliability will be:

A

Active Redundancy, 2 of 4 must work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What component reliability is required to achieve a two component series system reliability of 0.998,
if both components have the same reliability?

A

R(system) = R2(component) => √R(system)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Realizing a close parallel between injected faults and unknown faults, the software quality assurance group injected 40 errors into a software program. The testing program found a total of 210 faults, 30 of which were injected faults. Assuming all injected faults have been removed,

estimate the number of errors remaining in the software program.

A

Ratio between injected faults and original faults

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The seeding of errors into a program and counting the number of seeded versus identified defects allows the test engineer to estimate the number of:

A

Defects in the program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Typically statistical distributions or confidence limits can be determined for accelerated tests.

In the case of a step-stress test,
the proper estimated distribution would be?

A

None, not meaningful

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

One disandvantage of a full working design prototype is:

A

The time and cost to create the model

VII - 105

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The goal of a design prototype is to …

A

test products,

before investing in the final product

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

In order to attain a high order of series reliability …

A

The number of parts must be kept to a minimum .

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A system consists of a large number of different in-series components, none of which individually contribute very heavily to the total failure propability. A particular component that fails during operation is immediately replaced by another of the same type. An appropriate model for the
time between failure distribution for this system is the:

A

Exponential (VII - 53)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Failure rates in reliability analysis for the exponential case:

A

Are summed,

to combine independent series elements in reliability analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

In the logic diagram

RA = 0.90 ; 2 out of 3 and 
RB = 0.80 ; 2 out of 4 

What is the reliability?

A

System A and system B propabilities can be located from a binominal table.
Then treating the diagram as a series caluculation

R(system) = RA(system) * RB(system)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Electronic assembly screening tests would:

A

Eliminate manufacturing defects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

A steel alloy has a defined endurance limit.

For this material:

A

Stresses lower than the endurance limit will not cause failure regardless of the number of cycles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

A system consists of 4 parallel units each having a reliability of 0.80. The system can still complete its mission with only 2 units functioning.

If the failure rate is constant and failures are independent then the system reliability will be:

A

This is a binominal based voting system.

n = 4 ; r = 2 ; P = binominal table

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

The keynote component in the application of Bayes`theorem is:

A

A component that enhances the reliability of the system by its addition,
but still lets the system operate if it fails

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

-

A

-

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Equivalence class partitioning is:

A

A black-box method
that devides the inputs to a program into classes
from which test cases can be derived

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

A reliability expression for three independent components in parallel with component reliability R is:

A

3R - 3R - 3R^2 + R^3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

In determining the constant failure rate of a system based on test results of components that compromise the
system, why must the individual failure rates be summed instead of dividing total component test times by failures?

A

The components are assumed to fail independently (VII - 54)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

In an S-N diagram,

a point at which failure occurs in one cycle is called the:

A

Ultimate load

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Environmental stress screening has shown to be very effective in a production process.
The levels of defects have dropped form 5% to 25 ppm.

This would indicate:

A

ESS is still needed, but change the applied stresses.

If all defects have been eliminated ESS may be stopped.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Which theory is customarily used to calculate the life of a part as it undergoes various mechanical loadings over time?

A

Miner`s Rule

__
Die lineare Schadensakkumulation dient zur Beurteilung des Einflusses eines Lastkollektivs auf die Lebensdauer eines Bauteils

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

If environmental stress screening is required, what precentage of components should be screened?

A

100% (VII - 12)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

The design or discrimination ratio used in PRST (SPRT) is an expression of:

A

Accpetable MTBF / low limit MTBF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

In a software development project,

which of the following elements is essential to ensure a reliable product.

A

Ensuring that requirements based testing is performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

The effect of increasing the stress level on a component is to:

A

Decrease the mean wearout life for the component

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Which answer mathematically expresses the reliability of an active parallel system
in which all component reliabilites (Ra, Rb, Rc) are unequal?

A

Solve this algebracally as 1- unreliability

=> Rs = Ra + Rb + Rc - RaRb - RbRc - RaRc + RaRbRc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Which of the following represents a burn-in testing cost?

A

The burn-in chamber cost for the unit .

39
Q

If the exponential failure time distribution is assumed,

what is the reliabiliy prediction uncertainty as measure by the standard deviation?

A

1 / λ = MTBF

.., is the Standard deviation of the exponential distribution.

40
Q

A classification of tests used for products,

based on the ratio of an acceptable MTBF is:

A

Propability Ratio Sequential Testing

41
Q

The Beta distribution is useful for providing a lower confidence limit on a given reliability.

Given three failures,
if the given reliability is 0.90 and the desired confidence is 0.75,

what is the required sample size?

A

Requires use of Beta table: for 0.75 conf and 3 failures (n-r)
=> look for the lowest sample size that will yield a reliablity of 0.90

42
Q

The use of reliability data to determine when an individual unit will fail is an example of:

A

An improper use of reliability data and implications. (VII-98/102)

Reliability data cannot be used to predict when an individual unit will fail.

Reliability data is used to generate statements concerning the propability of a failure at any given time

43
Q

HASS test limits that are typically derived from previous HALT tests.

A

Highly accelerated life tests (VII-21)

44
Q

According to the definition of reliability,
performance over the expected or intended life is one criterion.

In order to obtain a measurement for reliability the actual life (t) must be compared to which of the following?

A

Required life

45
Q

Which term is best for defining the reliability of a repairable system such as a personal computer ?

A

MTBF

46
Q

The reliability of a complex system can best be improved by:

A

Including redundant concepts in the design

47
Q

DoD data indicates that environmental stress screeining can reduce field failure rates by:

A

20-90%

48
Q

Failure occur on a system at 75, 79, 83 and 85 hour. Assuming normality, one sided and unbiased,

the lower tolerance limit for 95% reliability with 90% confidence for this sample is:

A

TL = x̄ - KS

_
Calculate the mean (x̄) and sample standrad deviation (s) for the given numbers, based on given dataset

K = a constant found in Section X - 14 of CRE Primer.

49
Q

In a life test of 4 batteries, failures were observed after 10, 30 and 40 hours. The 4th battery was tested 75 hours without failure, at which time the test was terminated. What are the estimated MTTF (theta) and failure rate (lambda)?

A

Estimated MTTF = 52 ; Failure rate = 0,019 / theta = T/r ; λ = 1/theta / test terminated means time counted without failure

50
Q

The purpose of a burn-in operation on parts is to:

A

Remove weak units from the population

51
Q

ESS is best performed at which stage of the product life-cycle?

A

Production/Manufacturing (ESS, is a test or series of test used to pre-screen components druing production to reduce infanct mortality)

52
Q

Electronic assembly screening tests would:

A

Eliminate manufacturing defects

_
Screening test are used, particulary in electronic assemblies and componets to eliminiate manufacturing defects therby increasing the reliability and decreasing the short term failures in the filed. Screening tests are not used to eliminate design defects. Design defects should be discorvered and eliminated in development testing.

53
Q

To eliminate potential defects or errors during production, the QE and RE should

A

Develop pre- production plans

54
Q

Which type of software testing is performed after modifications are made?

A

Regression

55
Q

Which method is best for finding a failure mechanism in a semiconductor device?

A

Eddy current NDT

56
Q

When analyzing a design for reliability, which method is used?

A

Load-stregth analysis

57
Q

When designing for mechanical reliability, which factor should be included in the study?

A

Stop / Starts

58
Q

Which tool is best used to determine if problems are sporadic or chronic problems?

A

Pareto analysis

59
Q

A DOE is conducted, which tool is used to analyze the relationship between the factors and the responses?

A

Main effects plot

60
Q

If failure times for all of the parts in a life test are analyzed, the resulting data is

A

complete

61
Q

Censoring of reliability data indicates which of the following?

A

Testing has been failure terminated

62
Q

A weight of 26.581 kilograms would indicate a measurement that is:

A

Continous and unvariant

63
Q

The predicted reliability is higher than the long term realized propability. Which of the following is the most likely cause of this difference?

A

Deterioration of the manufacturing process and procedures

64
Q

A key element of the prototype process is:

A

Customer evaluation and feedback

65
Q

An engineer has determined that the mean diameter of the catheter fittings is always 15 mm. A CRE draws a random sample of nine (9) of the fittings was from stores.

Calculate the value of the appropriate test statistic to test the following: H0: u = 15 cm
xx, xx, ..

A

t = mean / Sx

_
First, put the values into the calculator and get the mean and Sx.

66
Q

A CRE is using an Arrhenius model and discovers that the activation energy varies with temperature deltas.
What conclusion can be drawn?

A

The part has multiple failure mechanisms

67
Q

In the intitial allocation of failure rates, system components are assumed to be

A

Serially connected

68
Q

The main reason for categorization in terms of occurence, severity and detection (FMEA) is ..

A

prioritize the failures for corrective action

69
Q

A parts-count reliability prediction is based on which model?

A

Basic series model

70
Q

In software reliability, an operational profile is used to determine

A

how the software will be used

71
Q

Why should a reliability engineer perform a finite element analysis (FEA) simulation to analyze the effect of complex loading situations on various material properties?

A

The mesh size of the model has an impact on the simulation result.

72
Q

Which degradation model is distribution free?

A

Proportional hazards

73
Q

Which statement is the best desription of environmental stress screening (ESS)?

A

It`s useful in weeding out defects using either normal or accelerated tests.

74
Q

The seeding of errors into a program and counting the number of seeded versus identified defects allows a test engineer to estimate the number of:

A

Defects in the program

75
Q

A system has three components with reliability values, A, B and C.

The reliability of the system R can be calculated using the equation:

A

Insufficient information has been provided

76
Q

White-box testing is distinguished from black-box testing by:

A

Use of the control structure to derive test cases

77
Q

Discovery testing is used early in the development cycle to:

A

Show weaknesses of the design

78
Q

Which kind of test demonstrates successful operation without failure?

A

Margin test
_
The margin test is designed to demonstrate a unit operates succesfully with a margin of safety.

79
Q

Which conditions is an example of a non-material failure mode?

A

Electromagnetic interference

80
Q

Applied stress divided by rated maximum stress is the formula for calculating a …

A

safety margin

81
Q

To eliminate potential defects or errors during production, the QE and RE should …

A

develop pre- production plans

82
Q

Which type of software testing is performed after modificatons are made ?

A

Regression

83
Q

Which method is best for finding a failure mechanism in a semiconductor device?

A

Eddy current NDT

84
Q

When analyzing a design for reliability, which method is used ?

A

Load-strength analysis

85
Q

For overall visual understanding, which data is best presented in a graphical format ?

A

Data Distributions

86
Q

Which tool is best used to determine if problems are sporadic or chronic problems ?

A

Pareto analysis

87
Q

Large sample means tend to be normally distributed and clustered around the the population mean because which theorem ?

A

Central limit

88
Q

Which method is used to analyze the effects of residuals for a 2³ or 2ᶰ¯¹ factorial experiments ?

A

Normal probability plot

89
Q

A DOE is conducted, which tool is used to analyze the relationship between the factors and the responses ?

A

Main effects plot

90
Q

A parts-count reliability prediction,

is based on which model?

A

Basic series model

91
Q

If a CRE applies statistical inference techniques to assess the reliability of current software during a system test,
what type of measurement is the engineer using?

A

Estimation

92
Q

The main reason for categorizing failures in terms of occurrence, severity, and detection (FMEA) is to …

A

prioritize the failures for corrective action

93
Q

Life data that is right-censored and time based time-based reveals failures that …

A

go beyond the present time

94
Q

A CRE uses randomization in experiments in order to minimize

A

bias (Voreingenommenheit)