Maintainability Flashcards

1
Q

“The propability that a failed system will be restored to an operational condition with a specified time” is a definition of:

A

Repairability (IX - 2/3)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Reliability active time includes what two major components?

A

Up time and down time (IX - 4)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

An appropriate preventive maintenance programm can greatly increase the overall availability of a system because of:

A

An increase in observed reliability (IX - 6/11)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The “gold in the mine” for repairability and maintainability is:

A

The savings on maintenance and logistics (IX - 37)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A designer`s responsibility is to include maintenance considerations in any design. The considerations should include:

A

Reduction and ease of maintenance (IX - 2 and 37)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

In a total productive maintenance (TPM) environment, the operator is trained to handle small and routine repairs
to the equipment (use of autonomous group activities). Skilled maintenance craftman are still required for the heavy duty, specialized areas of repair and restoration.

A

The equipment operators perform routine equipment maintenance (IX - 11)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The optimum parts replacement policy that attempts to determine the replacement age therby minimizing the downtime per unit of time is called:

A

Preventive replacement at predetermined age (IX - 19)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A preventive maintenance program that follows the philosophy of optimum parts replacement will have:

A

Some failures (IX - 15/21)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What kind of failure would most likely result fom insufficient hardware debugging?

A

Early failure ( IX - 7)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which of the following is the reason the bathtub curve has an increasing failure rate during wear-out period?

A

Design, materials and environment determine a limit of useful life (IX - 34/35)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Preventive maintenance can be justified as cost effective when:

A

The corrective maintenance cost can be significantly reduced (IX - 32/38)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is System Effectiveness, if Operational Readiness is 0.89, Design Adequacy is 0.95, Availability is 0.98, Maintainability is 0.93 and Mission Reliability is 0.99?

A

System Effictivfeness = Mission Reliability x Operational Readiness x Design Adequacy (IX - 3 ; 0.837)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Maintainability is the propability of:

A

An item to be retained or restored to a specific condition for a specified mission (IX - 10/12)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Historical data has shown for a particular electronic component that it experiences infant mortality and then a constant failure rate thereafter. For this component:

A

Performing preventive maintenance increases the failure rate (IX - 7)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The optimum time between maintenance actions is:

A

Found by minimizing the total cost per unit time (IX - 19)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What would be the spares required for 100 units at a failure rate of 2000 x 10^-9 failures per operation hours? The operating time is 4000 hours. The level of confidence is 0.95.

A

a) calculate => Spares/unit = lambda * t + Z √ lambda * t

b) For 100 units, spares = 100 * # Spares/unit ( IX - 25)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

It is often observed that unscheduled maintenance:

A

Does not necessarily isolate failure causes (IX - 36

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

In consideration of the life histroy curves of complex products

a reliability centered maintenance approach would indicate that …

A

Some items are better left alone

(IX - 7)

19
Q

Given a Weibull failure distribution for an extruder producing packaging film with g =400 hours, b=1.5, h=700 hours. The cost of a scheduled PM action is $5,000, while the cost of an unexpected failure is $15,000. The line operates as 8,760 hours per year and scheduled PM is now set at every quarter. Determine the approximate costs for the existing PM schedule.

A

C = PM Cost + Failure Cost (IX - 18)

20
Q

High cycle fatigue would most likely result in:

A

Wear out failure (IX - 7)

21
Q

The objective of using a constant interval replacement policy is to:

A

Minimize the total downtime and to minimize the unavailability of the equipment (IX - 19)

22
Q

If a component experiences infant mortality but does not experience aging during its life then:

A

A system overhaul leads to additional infant mortality possilbilities (IX - 7)

23
Q

A total productive maintenance is a program in which:

A

Equipment maintenance is shared between operators and maintenance personnel (IX - 10/11)

24
Q

The maintenance time needed to replenish consumables and check out an item for recommitment is called;

A

Turn around time

IX - 5

25
Q

The basic maintainability requirements for a system or component are best determined via:

A

Analysis of customer requirements (IX - 2/3)

26
Q

Preventive maintenance policies are best applied when:

A

The system has an increasing hazard rate (IX - 7 and 35)

27
Q

If the assumption is met that a repairable system has a constant failure rate while up and repair restores the system to its previous failure rate, which of the following implications it true?

A

Burn-in would not be effective (IX - 34/35)

28
Q

Fault isolation is rarely facilitated by using which of the following?

A

Corrective maintenance (IX - 32/33 and 37/38)

29
Q

The effectiveness of a maintenance program is affected most by:

A

Designed ease of installation and removal of components (IX - 36/38)

30
Q

When forecasting needed spares based on field data, what is the formula for total wait time?

A

1 / rapair rate - failure rate (IX - 30)

31
Q

The maintenance time constraint (t) is:

A

Usually prescribed as a requirement of the mission (IX - 2/5)

32
Q

A project engineering team did a good job of building a plant in modules and standardizing as much as possible. There was high inherent reliability in the installed equipment and machinery. The maintenance department demand for repair and replacement parts was very low for the past year. During the next few months there is a big spice in replacement parts. This can be explained as:

A

WEAP (Warranty expiration anticipation phenomenon)

The part to be replaced has not worn out as of yet but the warranty is due to expire and good practice might dictate that parts be changed out on scheduled even if not needed. This would cause the spice ( IX - 21)

33
Q

In order to sustain a high system reliability in the field it is best to:

A

Follow a preventive maintenance program with scheduled diagnostic checks (IX - 32/38)

34
Q

The following information pertains to a wheel hub that has five bolts.

  • The unreliability of each bolt is 0.001
  • Four wheel bolts are adequat to perform the designed function
  • Failures are independent

What is the reliability of the system?

A

Binominal table for p=.005 ; n=5 ; r=1 or

35
Q

The average rate for patient arrival at a hospital is 2 patients per hour. If the arrival rate follows a Poisson distribution, what is the propability of exactly 2 patients arriving in one hour?

A

1) look up in Poisson table
2) It is equal to the propability of exactly 1 patient arriving

np = 2 ; r = 2 = 0.2707 / r = 1 = 0.2707

36
Q

A fault tree analysis (FTA) uses which of the following elements to determine the propability of a predetermined event occuring?

A

Boolean algebra

37
Q

A component has a Weibull failure distribution with a shape parameter of 0.8 and scale parameter of 300 hours.

Scheduling replacement every 200 hours will result in which of the following outcomes?

A

Descreased failure rate

38
Q

The reliability centered maintenance (RCM) approach has potential for use in many areas of industry, having been
successfully emplayed in the aircraft and nuclear power industries. A major premise of RCM is which of the following?

A

Preserve system function (IC - 6/9)

39
Q

What would be the spares required for 100 units at a failure rate of 2000 x 10^-9 failures per operation hours? The operating time is 4000 hours. The level of confidence is 95%.

A

Spares/unit = lambda t + Z √ lambda t (IX-25 ; 15,5 spares)

40
Q

High cycle fatigue would most likely result in:

A

Wear out failure (IX-7)

41
Q

Total productive maintenance seeks to eliminate the “six big losses.”

Which is included in the downtime category?

A

Setup losses

42
Q

What is the first step when conducting a maintainability study for a piece of existing equipment?

A

Identifying the problems that are causing the majority of downtime

43
Q

The result of a maintainability analysis should include:

A

The support equipment and tools required