As part of project planning, you refer to organizational practice and defined tolerance limits. Which of the following includes the key areas where tolerance limits are set?
SELECT THE CORRECT ANSWER

Quality, budget

Budget, time, quality, and non-functional requirements

Budget, time, and quality

Scope, schedule, and cost

A

Correct Option:B

EXPLANATION

Besides setting a tolerance limit for budget, quality, and time, you also need to define acceptable limits for deviations (non-compliances) for non-functional requirements. This will help you as a project manager to move forward swiftly with minimal escalations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

7
Tracking compliance information, including the proof of validation for each deliverable, is generally done as part of:
SELECT THE CORRECT ANSWER

Scope management

Stakeholder management

Risk management

Configuration management

A

Correct Option:D

EXPLANATION

One of the key attributes to be tracked is compliance of a deliverable with a defined requirement. Tracking the proof for validation of the compliance of the deliverable is done as part of configuration management (although it might sound like compliance management).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

9
A risk breakdown structure is created as part of:
SELECT THE CORRECT ANSWER

Risk qualitative analysis

Risk identification and categorization

Risk response

Risk ownership

A

Correct Option:B

EXPLANATION

Once the risks are identified, they are categorized based on the source, like external, internal, technical, and project management. This gives the risk breakdown structure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

15The data analysis technique used to identify different ways of collecting requirements to elaborate on project and product scope is called:
SELECT THE CORRECT ANSWER

Design of experiments

Iterative gathering

Alternative analysis

Brainstorming

A

Correct Option:C

EXPLANATION

Alternative analysis is the evaluation of various ways in which requirements can be collected from stakeholders, and this can have an impact on the scope management plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

23Which of the following tools help you identify quality issues in the project? (Choose two)
SELECT THE CORRECT ANSWER(S)

Audits

Histograms

Design thinking

Control charts

A

Correct Option:A, D

EXPLANATION

Control charts will help in analyzing the process control and potential issues.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

29Common tools to track the performance of a team in AGILE include: (Choose two)
SELECT THE CORRECT ANSWER(S)

Scrum or Kanban board

Throughput

Project board

Blackboard

A

Correct Option:A, B

EXPLANATION

Common tools to track the performance of team in AGILE includes: Scrum or Kanban board and throughput.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

42Business risks impact the project. Choose three business risks from the following:
SELECT THE CORRECT ANSWER(S)

Competitive

Scope related

Legislative

Operational

A

Correct Option:A, C, D

EXPLANATION

Competitive, legislative, and operational risks are the business risks that impact the pr

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

46Joe, the project manager, believes in empowering the team as a definite means to achieve performance. It was agreed that the team would decide on all issues through consensus. One of the team members brings to the notice of Joe that decisions are arriving very late and that is impacting the project. What should Joe do to correct the situation?
SELECT THE CORRECT ANSWER

Ask the team to re-create the team charter

Get into problem solving directly

Suggest the team to have timelines for resolution

Let the team decide

A

Correct Option:C

EXPLANATION

This is the best option since the problem should not recur.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

54You and your team are finalizing the project’s scope statement. The scope statement contains: (Choose two)
SELECT THE CORRECT ANSWER(S)

Work, deliverables

Assumptions and constraints

Resources

WBS

A

Correct Option:A, B

EXPLANATION

Scope statement includes description of work, deliverables, assumptions and constraints.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

65Your team is in the process of finalizing the type of contract for procurement. It is observed that the procurement statement of work is not precise and there are some constraints which do not permit further clarity in defining the statement of work. It is agreed amongst stakeholders that the team can go for a slightly open-ended and flexible arrangement with the seller. Which of the following contract types would be best suited?
SELECT THE CORRECT ANSWER

Fixed price incentive fee contracts

Cost plus fixed fee

Time and materials or T and M

Fixed price-EPA

A

Correct Option:C

EXPLANATION

Time and materials or T and M contract works best for flexible arrangements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

67You are starting a new space related project. A project charter has been created and handed over to you. What is the next step?
SELECT THE CORRECT ANSWER

Sign the charter for acceptance

Start planning

Identify stakeholders

Identify risks

A

Correct Option:C

EXPLANATION

The next step is to identify stakeholders in the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

69One of your key stakeholders wants to review the product’s completion by comparing it against the requirements. Which document would you present to him?
SELECT THE CORRECT ANSWER

Project scope statement

Product requirements

WBS dictionary

Requirement traceability matrix

A

Correct Option:B

EXPLANATION

Completion of product scope is compared against product requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

87As a project manager, you are aware of the different stages of team formation as defined by Tuckman. Your team members are currently conversing with one another, attempting to understand the work and determining who will do what. Which stage is your team in now?
SELECT THE CORRECT ANSWER

Stage 2

Stage 1

Stage 5

Stage 4

A

Correct Option:A

EXPLANATION

The 5 stages are forming, storming, norming, performing, and adjourning. Now the team is in the second stage of storming.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

95For what do quality audit findings become a good source? (Select all that apply)
SELECT THE CORRECT ANSWER(S)

Gaps and shortcomings

Validation of quality tools

Lessons learned

Effectiveness of audit team

A

Correct Option:A, C

EXPLANATION

A quality audit identifies the gaps and shortcomings for improvement. They also become a good source of lessons learned.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

102What technique is used to consolidate ideas, created through individual brainstorming sessions, into a single map to reflect commonality and differences in understanding, and to generate new ideas?
SELECT THE CORRECT ANSWER

Decision tree analysis

Mind mapping

Affinity diagram

SWOT analysis

A

Correct Option:B

EXPLANATION

It is the data representation technique for understanding the requirements into a single map to reflect commonality and differences in understanding and to generate new ideas.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

109…………….. is an approach to improving business results through an emphasis on customer satisfaction, employee development, and processes rather than functions.
SELECT THE CORRECT ANSWER

Six Sigma

TQM

Lean Six Sigma

Kaizen

A

Correct Option:B

EXPLANATION

Total quality management is an approach to improve customer satisfaction by managing the quality processes and people involved in a better manner across the organization.

17
Q

110The advantage of the Minimum Business Increment (MBI) is all of the following, except
SELECT THE CORRECT ANSWER

Enable team to deliver value sooner

Validate if improvement has taken place

Helps business grow

Provides the building block for the team to proceed further

A

Correct Option:C

EXPLANATION

MBI does not help the business to grow.

18
Q

112What is the key attribute of continuous improvement?
SELECT THE CORRECT ANSWER

Lowering costs

Minimizing changes to product or service

Improving stakeholder support

Better designing of product

A

Correct Option:D

EXPLANATION

Better design of products is the key attribute of continuous improvement measures.

19
Q

113The key elements of a communication management plan include all of the following, except
SELECT THE CORRECT ANSWER

List of stakeholders

Frequency of communication

Method of communication

Risks in communication

A

Correct Option:D

EXPLANATION

The risks are captured in the risk register.

20
Q

117The true test of effective training is demonstrated by ………………
SELECT THE CORRECT ANSWER

Increase in efforts

Increase in documentation

Increase in skill on the job

Increase in team bonding

A

Correct Option:C

EXPLANATION

An increase in skills on the job signifies productivity. Hence, this is the real measure of the effectiveness of training.

21
Q

119As a project manager, you have identified the root cause of a quality problem and have identified the corrective action required. A change request is initiated and approved. Next you update the project plan to reflect the changes. What is the next step?
SELECT THE CORRECT ANSWER

Document the causes of the variances and the steps taken to correct them

Prepare a report

Inform the customer

None of the above

A

Correct Option:A

EXPLANATION

The changes made have to be updated in the plan along with the causes identified.

22
Q

123You, as a project manager, are looking into defining an approach for subsequent releases by looking into availability of a set of features, time adherence for release and organizational tolerance for changes. What are you into?
SELECT THE CORRECT ANSWER

Configuration management

Product scoping

Release management

Tolerance definition

A

Correct Option:C

EXPLANATION

Planning for subsequent releases is referred to as release management.

23
Q

125Name the systematic approach that is used to estimate the strengths and weaknesses of alternatives and to determine options which provide the best approach to achieve benefits while preserving savings.
SELECT THE CORRECT ANSWER

Root cause analysis

Benefit cost analysis

Data analysis

What-if analysis

A

Correct Option:B

EXPLANATION

Benefit cost analysis helps to analyze the alternatives and provides benefits while preserving savings.

24
Q

129The objective of an AB Testing experiment is to
SELECT THE CORRECT ANSWER

Obtain trust of the customer

Ensure willingness of sponsor to invest

Enhance customer delight

Optimize the solution to the customer

A

Correct Option:D

EXPLANATION

AB Testing provides insight into a customer’s preference for one solution over the other.

25
142In a hybrid lifecycle project, how will a product be delivered? SELECT THE CORRECT ANSWER As single product delivery at the end As product increments, based on value As work packages of WBS None of the above
Correct Option:B EXPLANATION Multiple incremental deliveries are made in a hybrid lifecycle project.
26
146You are leading a project that requires machinery. You have ordered the machinery, spares and other equipment required. You are allocating the space required for their installation. You are also earmarking some battery banks for backup power. What are you involved in? SELECT THE CORRECT ANSWER Physical resource mobilization Physical resource assignment Resource histogram Resource breakdown
Correct Option:B EXPLANATION Physical resource assignment includes fulfilling machinery requirements that you need for the project.
27
148The components of Mckinsey's 7S model for organizational change include all of the following, except SELECT THE CORRECT ANSWER Strategy Solution Shared values Structure
Correct Option:B EXPLANATION 7S includes strategy, structure, systems, shared values, skills, style, and staff.
28
153Active listening includes three components, that are: SELECT THE CORRECT ANSWER Understanding, reflecting, and confirming Reflecting, attending, and following Attention, reflection, and action None of the above
Correct Option:B EXPLANATION These are 3 components of active listening-reflecting on what the person is saying, displaying changes in verbal and nonverbal behavior when the person is speaking, and confirming through questions to understand.
29
162Which of the following is NOT a guideline for conducting retrospectives? SELECT THE CORRECT ANSWER Preparing for areas of focus Having a moderator Finding faults Arriving at a consensus on areas for improvement
Correct Option:C EXPLANATION Retrospectives are not used to find faults but to identify areas for improvement for the next sprint.
30
168You decide to manage your team by setting objectives and tracking their performance. Which is the best way to go about setting objectives? SELECT THE CORRECT ANSWER Throughout the life cycle At the end of the phase Annually During the retrospective
Correct Option:A EXPLANATION It is best to track the performance of the team throughout their life cycle as a part of iteration planning.
31
169As a project manager, you are aware that continuous feedback is essential for agility. What is the prime responsibility of a project manager when it comes to feedback? SELECT THE CORRECT ANSWER Removing noise factors Ensuring communication protocols are maintained Ensuring appropriate and timely feedback Selecting the right medium for communication
Correct Option:C EXPLANATION Timely feedback is critical for conducting corrective actions.
32
173\_\_\_\_\_\_\_\_\_\_\_ is a nominal group technique (NGT). SELECT THE CORRECT ANSWER Making group decision Brainstorming with the group for ideas Making group decisions using voting Collecting user stories in a sprint
Correct Option:C EXPLANATION Making group decisions using voting is an NGT.
33
174Social skills are necessary for the project manager and all team members. Social skills include all of the following except: SELECT THE CORRECT ANSWER Communication Leadership Empathy Building bonds
Correct Option:C EXPLANATION Empathy is an interpersonal skills and not a social skill.
34
175Emotional Intelligence includes personal and interpersonal skills. What does personal skills include? (Select all options that apply) SELECT THE CORRECT ANSWER(S) Motivation Empathy Self awareness Considerate
Correct Option:A, C EXPLANATION Self awareness and motivation are personal skills.
35
176Being accountable for goals and well-ordered, satisfying obligations, and having a meticulous approach to work are all examples of being: SELECT THE CORRECT ANSWER Disciplined Good mannered Kind Conscientious
Correct Option:D EXPLANATION Being accountable for goals and well-ordered, satisfying obligations, and having a meticulous approach to work are all examples of being conscientious. This is an attribute of self-regulation that leads emotional intelligence.
36
177Which of the following is an important element of the project management plan that keeps the business in mind? SELECT THE CORRECT ANSWER Change management plan Compliance management plan Configuration management plan Business management plan
Correct Option:B EXPLANATION The compliance management plan contains the compliances required for the project and keeps the business in mind.