Test 3 Flashcards
2A project team is performing the work of the project to achieve its objectives. Which of the following is not potentially a project team?
SELECT THE CORRECT ANSWER
Project management staff who perform budgeting and reporting.
Project staff who create project deliverables.
Customer representatives who provide requirements
Stakeholder group
Correct Option:D
EXPLANATION
Stakeholder group is the larger group of people and organisations and not all are part of the project team
12An important feature in Agile is to maintain a prioritized list of backlog. Which of the following is NOT a prioritization technique?
SELECT THE CORRECT ANSWER
Monte Carlo simulation
Kano model
MoSCoW analysis
100 Points Method
Correct Option:A
EXPLANATION
Monte Carlo simulation is a technique used to understand the impact of risk and uncertainty in prediction and forecasting models.
20Agile has certain ceremonies like daily standup, sprint review, and sprint retrospective. Which of the following is not true about the ceremonies?
SELECT THE CORRECT ANSWER
Daily standups are status meetings.
Sprint planning is a collaborative event for planning the project release.
Both A and B are wrong
Both A and B are correct
Correct Option:C
EXPLANATION
Sprint planning plans the work for the current sprint, not an entire project. Daily standups are not status meetings. The are required for a team to reaffirm commitment to its objectives, coordinate work among team members, and surface potential blockers.
39Which of the following is NOT a tool/technique for verifying scope?
SELECT THE CORRECT ANSWER
Definition of Done
Definition of Ready
Acceptance Criteria
Team review comments
Correct Option:D
EXPLANATION
DOD, DOR, and Acceptance criteria are tools and techniques for verifying the scope.
43A charter for a simple project without much dependency is approved, and the team is working on Iterative scheduling. Which of the following is NOT true about Iterative scheduling?
SELECT THE CORRECT ANSWER
The method uses progressive elaboration
Iterative scheduling works best for complex projects with dependency
Stories that provide the highest value are prioritized
Stories are prioritized based on how long they take
Correct Option:B
EXPLANATION
Iterative scheduling with a backlog does not work well with activities that have complex dependency relationships.
47An Agile team is preparing for its retrospective. Which of the following is NOT correct about retrospectives?
SELECT THE CORRECT ANSWER
A retrospective is a review of what went well
A retrospective is a review of what could have been done better
A retrospective assesses team collaboration.
The product owner is not included as this is for the agile team
Correct Option:D
EXPLANATION
A retrospective meeting consists of the agile team, product owner, and key stakeholders
53Value stream mapping is used to:
SELECT THE CORRECT ANSWER
Develop earned value management
Develop expected monetary value
Analyze flow of information
Compute overall value of the project
Correct Option:C
EXPLANATION
Value stream mapping is used to document, analyze, and improve the flow of information or materials required to provide a product or service for a customer.
55Impediments and blockers can be identified at various stages by the team. Which of the following is NOT true about impediments?
SELECT THE CORRECT ANSWER
Can be uncovered during daily standups.
Can be represented using sticky notes on a whiteboard
Can be tracked using sophisticated software
Cannot be a result of project risks
Correct Option:D
EXPLANATION
Impediments may be due to or as a result of project risks or issues.
62Some of the senior team members in a project are classifying compliance. The team comes up with a list of categories, which includes environmental risk, Workplace safety, corrupt practices, social responsibility, quality, and process risks. The architect does not agree that social responsibility and process risks are categories for compliance. The test lead believes that process risks is a correct category but social responsibility does not have any meaning and cannot be considered a compliance category. The development manager states both social responsibility and process risks can be part of the compliance category classification. Who is correct about compliance categories classification?
SELECT THE CORRECT ANSWER
Architect
Development Manager
Test Lead
None of the above
Correct Option:B
EXPLANATION
There are many different types of compliance categories that may be necessary for a particular industry and solution scope. This may include social responsibility and process risks.
66Which of the following is done by QA?
SELECT THE CORRECT ANSWER
Review the deliverable so that it meets functional and nonfunctional requirements
Suggest potential improvements
Make recommendations to address any noncompliance
All of the above
Correct Option:D
EXPLANATION
As the project team produces deliverables, quality assurance (QA) will review the deliverable, verify that it meets functional and nonfunctional requirements, and often identify and suggest potential improvements. QA will validate whether the deliverables align with compliance requirements and provide feedback on any variances.
68Quality audits are used to verify compliance and are generally conducted by an external team. Audits are generally used to: (Choose all options that are correct)
SELECT THE CORRECT ANSWER(S)
Share good practices from other projects in the organisation or industry
Highlight contributions to lessons learned
Identify critical path
None of the above
Correct Option:A, B
EXPLANATION
Quality audits are used to verify compliance with organizational policies, processes, and procedures. They are generally used to identify good practices being used, share good practices from other projects, proactively offer improvements to improve productivity, and highlight contributions to lessons learned.
70A project management plan can contain many subsidiary plans. Which of the following is not correct about Benefits Management Plan?
SELECT THE CORRECT ANSWER
It describes how the benefits of a project will be derived.
It describes how the benefits are measured.
It is a subsidiary component of the project management plan.
It describes when the benefits will be realized, usually by project phase.
Correct Option:C
EXPLANATION
Benefits Management plan is a business document and is not a subsidiary component of the project management plan.
76TQM is an approach to improve business results. Which of the following is NOT true about TQM implementation by quality theorists?
SELECT THE CORRECT ANSWER
Juran trilogy breaks quality management into quality planning control and improvement.
Taguchi method emphasizes that quality should be designed into the product.
Deming cycle is focused on one-time fix for quality to meet customer needs.
Six sigma emphasizes responding to customer needs by systematically removing defects.
Correct Option:C
EXPLANATION
Deming cycle focuses on continuous process improvement in which quality must be continuously improved to meet customer needs.
78Which of the following statements is NOT true about a product life cycle?
SELECT THE CORRECT ANSWER
It starts with conception of a new product and ends with its withdrawal.
A product can spawn a single project in its life.
The five stages of each product lifecycle are product development, introduction, growth, maturity, and decline.
It focuses on managing the properties of a product from a company’s business point of view.
Correct Option:B
EXPLANATION
A product can spawn a single project in its life. Product lifecycle management (PLM) is the process of managing the entire lifecycle of a product from its conception, through design and manufacture, to service and disposal. PLM integrates people, data, processes, and business systems to provide a product information backbone for companies. The five stages of each product lifecycle are product development, introduction, growth, maturity, and decline. A product can spawn or require many projects over its life.
85Jenny is a Project Manager and is currently in the initiating process group. She understands that it is critical for project success to identify stakeholders early in the project. Therefore, she is in the Identify Stakeholders process. Of the following, which INPUT may not be required?
SELECT THE CORRECT ANSWER
Project documents
Project Charter
Expert Judgment
Enterprise environmental factors
Correct Option:C
EXPLANATION
Expert judgment is a tool and technique for the Identify Stakeholders process and is not an input
86One phase is planned at any given time, and the planning for the next is carried out as work progresses on the current phase and deliverables. Which of the following correctly defines the above text?
SELECT THE CORRECT ANSWER
Overlapping relationship
Sequential relationship
Multi-phase relationship
Iterative relationship
Correct Option:D
EXPLANATION
An iterative relationship is where one phase is planned at any given time, and the planning for the next is carried out as work progresses on the current phase or deliverable.
90Which of the following is NOT a function of the project management office?
SELECT THE CORRECT ANSWER
Monitoring compliance with project management standards policies, procedures, and templates via project audits
Coaching, mentoring, training, and oversight
Managing shared resources across all projects administered by PMO
Identifying and developing the organization’s methodology, administrative practices, and rules
Correct Option:D
EXPLANATION
The PMO’s role is to identify and develop the project management methodology, best practices, and standards.
93Two members of a team are disagreeing about the right electric parameters for testing a newly designed chipset. Who is in the best position to help resolve this issue?
SELECT THE CORRECT ANSWER
Project Manager
Project Sponsor
Functional Manager
Customer
Correct Option:C
EXPLANATION
The issue requires functional expertise, so the Functional Managers will be in the best position to assist in this matter.
104As a Project Manager, you are estimating the duration of your project activities using PERT technique (Program Evaluation and Review technique). For a particular project activity, your optimistic estimate is 41 days, pessimistic estimate is 89 days, and most Likely estimate is 60 days. What would be the expected duration and range of estimate for this activity?
SELECT THE CORRECT ANSWER
- 67 +/- 8.00
- 27 +/-8.00
- 67 +/-3.00
- 27 +/-3.00
Correct Option:A
EXPLANATION
PERT allows the estimator to include three estimates: optimistic, pessimistic, and most likely, given by the equation Expected Duration = [P + 4(ML) + O]/6. Range is +/- standard deviation = (P-O)/6, where P is the pessimistic estimate, ML is the most likely estimate, and O is the optimistic estimate. Using this method, the correct answers comes out to be 61.67 days and range (+/-Standard Deviation) is 8.00.
107A Project Manager understands the information needs of important stakeholders and documents how they would be met. Which document is being prepared?
SELECT THE CORRECT ANSWER
Stakeholder register
Stakeholder management plan
Human resources management plan
Communications management plan
Correct Option:D
EXPLANATION
Communications management plan contains details of how the communication needs of the project’s stakeholders will be met.
110Which of the following are the MOST important to derive the total funding requirements and periodic funding requirements of the project?
SELECT THE CORRECT ANSWER
Management Reserve and Contingency Reserve
Cost Baseline and Management Reserve
Funding Limit Reconciliation
Project Budget and Contingency Reserve
Correct Option:B
EXPLANATION
The total funds required in the project are those included in cost baseline, plus management reserve if any. Remember, the cost baseline includes contingency reserves because the cost baseline will include projected expenditures plus anticipated liabilities.
111As a Project Manager for the project in the planning stage, you have derived the cost estimate by estimating the cost of individual work packages. It is summarized to higher levels for reporting and tracking. What would be the range of estimate from the actual?
SELECT THE CORRECT ANSWER
- 50 percent to +100 percent
- 50 percent to +50 percent
- 10 percent to +25 percent
- 5 percent to +10 percent
Correct Option:D
EXPLANATION
This is the definitive range derived during the latter part of the project when project information is available in sufficient detail. The estimate could become more refined to a range of -5 percent to +10 percent from the actual. This estimate is usually derived using the bottom-up estimation technique.
113John, a project manager, wants to capture the details of activities, including their inputs, outputs, and interfaces with other processes, to enhance the value of the process. Which of the following documents would be MOST helpful?
SELECT THE CORRECT ANSWER
Project Management Plan
Quality Management Plan
Process Improvement Plan
Product Management Plan
Correct Option:B
EXPLANATION
Quality management plan would be most helpful as it considers the continuous improvement procedure.
126You are a Project Manager taking over a project midway. It is in the execution phase. You would like to know more about project deliverables, work required to complete those deliverables, project constraints, assumptions, etc. Which of the following documents would be MOST useful?
SELECT THE CORRECT ANSWER
Work Breakdown Structure (WBS)
Requirements Documentation
Activity List
Project Scope Statement
Correct Option:D
EXPLANATION
The Project Manager should refer to the project scope statement as it captures all the details related to the project scope, including product acceptance criteria, scope description, project deliverables, constraints, assumptions, etc. Options A and Option C define project scope at the smaller work package and activity level respectively. Option B, Requirements Documentation, captures requirements of the project related to quality, functional and non-functional aspects, support, etc. This is incorrect.