Terms Flashcards
Acceptance Criteria
A set of conditions that are met before deliverables are accepted by the customers or sponsors
Activity
A distinct, scheduled portion of work performed during the project. Usually stored in an activity list.
Actual Cost (AC)
The actual cost incurred for the work performed on an activity during a specific time period
Analogous Estimating
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. Also known as top-down estimating.
Assumption
A factor in planning processes considered to be true or real without proof or demonstration.
Backward pass
A critical path method technique for computing the late start and late finish dates by working backward through the schedule model from the project end date.
Baseline
The accepted version of a work product that can be changed using formal change control processes and is used as the basis for comparison to actual results.
Bottom-up estimating
A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the workbreakdown structure.
Budget at Completion (BAC)
The amount of all budgets established for the work to be performed.
Change control
A process whereby changes to documents, deliverables, or baselines related with the project are identified, documented, approved or rejected
Change Control Board
A formally commissioned group responsible for reviewing, assessing, approving, deferring, or rejecting changes to the project, and for recording and communicating such decisions.
Change Control System
A set of procedures that defines how modifications to the project deliverables and documentation are managed and controlled.
Change request
A formal proposal to change any document, deliverable or baseline in the project management plan.
Communications management plan
A component of the project management plan that describes how, when, and by whom information will be administered and distributed.
Configuration management system
A collection of procedures used to track project artifacts and monitor and control changes to these artifacts.
Constraint
A restrictive feature that affects the execution of a project.
Contingency reserve
Time or money assigned in the schedule or cost baseline for known risks with response strategies.
Corrective action
A planned activity that restores the performance of the project work with the project management plan.
Cost baseline
The approved version of work packages cost estimates and contingency reserve that can be changed using formal control procedures.
Cost Management Plan
A component of a project management plan that defines how costs will be planned and controlled.
Cost Performance Index (CPI)
A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Cost Variance (CV)
The amount of budget shortfall or surplus at a given point in time, expressed as the difference between the earned value and the actual cost.
Crashing
A schedule compression technique used to shorten the schedule duration by adding resources. This will generally increase the cost of the project.
Critical Chain Method
A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources.
Critical path
The sequence of activities that represents the longest path through a project, which determines the shortest and longest possible duration. Activities on the critical path have no float.
Critical Path Activity
An activity on the critical path in a project schedule.
Critical Path Method
A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths.
Decomposition
A technique used for dividing and subdividing the project deliverables into smaller, more manageable parts. Also used to subdivide the project activities.
Defect repair
An intentional activity to modify nonconforming product or product component.
Deliverable
Part of the product that is presented to the customer or stakeholders for acceptance.
Duration
The work periods required to complete an activity or work breakdown structure component, expressed in hours, days, or weeks.
Early finish date
The earliest an activity can finish without delaying the project end date.
Early start date
The earliest an activity can start without delaying the project end date
Earned Value (EV)
The amount of money worth of work actually accomplished on the project.
Earned value management
A methodology that combines scope, schedule and resource measurements to assess project performance.
Enterprise Environmental Factors
Conditions, not under the immediate control of the team that influence, constrain, or direct the project.
Estimate at Completion (EAC)
The forecast of the total cost of the project at the end based on the current spending rate of the proejct.
Estimate to Complete (ETC)
The amount of money that will be needed to complete the current project based on the current performance.
Fast tracking
A schedule compression technique in which activities or phases are done in parallel for at least a portion or their entire duration. This can increase risk on the project.
Finish-to-finish
A relationship in which a successor activity cannot finish until a predecessor activity has finished.
Finish-to-start
A relationship in which a successor activity cannot start until a predecessor activity has finished.
Forward pass
A critical path method technique for calculating the early start and early finish dates by working forward through the schedule.
Functional organization
An organizational structure in which staff is grouped by areas of specialization and the project manager has limited authority.
Gantt chart
A bar chart of schedule information where activities are listed. Generally part of the project schedule.
Lag
The amount of time whereby a successor activity will be delayed to a predecessor activity.
Late finish date
The latest an activity can finish without delaying the project end date.
Late start date
The latest an activity can start without delaying the project end date.
Lead
The amount of time where a successor activity can be started before the predecessor activity finishes.
Lessons learned
The data gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance.
Logical relationship
A dependency between two activities.
Management reserve
Time or money that management puts aside in addition to schedule or cost baseline and issues for unforeseen work that is within the scope of the project. This is not under the control of the project manager and will need an approved change request to access it.
Matrix Organization
An organizational structure in which the project manager shares authority with the functional manager.
Milestone
A significant point or event in a project.
Milestone schedule
A type of schedule that presents milestones with planned dates.
Most likely duration
An estimate of the most probable activity duration that takes into account all of the known variables.
Network path
A sequence of activities linked by logical relationships in a project schedule network diagram
Opportunity
A risk that would have a positive effect on one or more project objectives.
Optimistic duration
An estimate of the shortest activity duration that takes into account all the known variables.
Organizational Process Assets
Plans, processes, policies, procedures and knowledge bases specific to and used by the performing organzation.
Parametric Estimating
An estimating technique in which an algorithm us used to calculate cost or duration based on historical data and project parameters.
Path convergence
A relationship in which a schedule activity has more than one predecessor.
Percent complete
An estimate expressed as a percent of the amount of work that has been completed on an activity.