tendering methods and management Flashcards

1
Q

What is tendering?

A

The main way a contractor obtains work by the submission and preparation of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is open tendering?

A

An advertisement by the client published in local newspapers or websites, allowing any interested contractors to place a bid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What happens at the close of the open tender period?

A

The quantity surveyor or project tenderer opens all tenders and makes recommendations to the architect and client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are some advantages of open tendering?

A
  • Very competitive
  • Only firms interested will submit tenders
  • New firms can find work and prove themselves
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is selected tendering?

A

A method where a project manager issues tender documents to a select list of contractors, usually ranging from 4-6.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a common practice under selected tendering?

A

It is usual to accept the lowest tender unless there are obvious mistakes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are some advantages of selected tendering?

A
  • Very competitive
  • Only selected firms submit tenders
  • Minimizes cost of tender
  • Mainly used for public works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are some disadvantages of selected tendering?

A
  • Not good for small contracts
  • New firms don’t usually get selected
  • Hard to get on tender list
  • Open to abuse
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is negotiated tendering?

A

A method where a contractor is chosen based on past performance or familiarity, often used for similar jobs with slight tweaks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a key advantage of negotiated tendering?

A

Allows earlier contract selection when the extent of work isn’t fully known and time is of the essence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a disadvantage of negotiated tendering?

A

Difficult for those in the public sector to negotiate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is serial tendering?

A

A method used for similar projects placed with a particular contractor, providing continuous flow of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are some advantages of serial tendering?

A
  • Flexibility
  • Cheap cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are some disadvantages of serial tendering?

A
  • Contract needs to be managed on both sides
  • Needs guaranteed amount of money for competitive prices
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is two-stage tendering?

A

A process where the client hires a project manager to present design and cost before inviting a contractor to complete a more in-depth tender.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the first stage of two-stage tendering focused on?

A

Producing a competitive tender based on approximate bills of quantities using preliminary design information.

17
Q

What is an advantage of two-stage tendering?

A

The contractor helps with design, leading to adherence to cost and time.

18
Q

What factors may affect tender cost?

A
  • Time
  • Size of tender list
  • Tenders with no specific start date
  • The type of contract
  • Quality of tender documents
  • Location
  • Bond insurance and liquidated damages
  • Completion time
  • Payment terms
  • Amount of existing work in the system
  • Selection of subcontractor
19
Q

What is good practice in the selection of subcontractors?

A
  • Clear procedure for transparent competition
  • Ensure receipt of compliant tenders
  • Short tender list
  • Same conditions for all tenderers
  • Sufficient time and information for preparation
  • Confidentiality respected
  • Assessment and acceptance of tenders
  • Commitment to teamwork
20
Q

What is the role of the Construction Industry Board?

A

Establishes a code of practice for the selection of subcontractors.

21
Q

What are the steps in the qualification process for tendering?

A
  • Completion of tender list
  • Tender invitation and submission
  • Tender assessed
  • Tender approved and awarded
22
Q

Who chooses domestic subcontractors?

A

The main contractor.

23
Q

What does a conventional subcontractor provide?

A

A completed service.

24
Q

What is a labour-only subcontractor?

A

Subcontractors supplied with materials to perform work.

25
Q

What is a labour and plant subcontractor?

A

Subcontractors who receive materials from the main contractor.

26
Q

What is the purpose of going to tender for competitive prices?

A

To obtain competitive prices using one of the three types of tendering.

27
Q

What is a nominated subcontractor?

A

A subcontractor chosen by the client.

28
Q

What risk does a client take when using a nominated subcontractor?

A

If the subcontractor does not perform, it may affect the main contractor.

29
Q

What should be included in enquiries for materials?

A
  • Title and location of work
  • Description of materials
  • Approximate quantities
  • Date by which quotation is needed
  • Name of estimator
  • Quote date for deliveries
  • Firm or fluctuating price
  • Minimum discount terms
  • Limitations on access to site
  • Size of contract
  • Local sourcing of materials
  • Storage of materials on site
  • Quality of materials specified
  • Existing terms and account
  • Lead-in times for early payment
  • Methods of transport
  • Supply times