resource planning and management documents Flashcards

1
Q

What do subcontractors agreements typically contain?

A

Fixed prices or rates, insurance values, retention, variations, tolerance and deficits, suspension of works, payment mechanism, discounts, insolvency, determination, adjudication, programme/durations, payment date schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a reason for suspension of works on a construction site?

A

Finding archaeological remains on site, a dead body on site which is less than 100 years old, an industrial dispute between unions, terrorism dangers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does RFI stand for in construction management?

A

Requests for information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of an RFI?

A

To require further information due to specifications/drawings not working on site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does CVI stand for?

A

Confirmation of verbal instruction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a CVI used for?

A

To record variation orders carried out without written instruction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What must be done with a CVI after it is filled out?

A

Must be in writing to the client within 3 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a day sheet in construction?

A

A record for day work items carried out without written instruction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does valuation involve?

A

Viewing what’s been done and paying accordingly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

List some components included in valuations.

A
  • Prelim section-management
  • Front payment summary sheet
  • Measured work section
  • Estimated total account figure
  • Day work schedule
  • Variation schedule
  • Materials on site schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the purpose of a vesting certificate?

A

To prove materials are paid before delivered to site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the significance of a front payment summary sheet?

A

It outlines what the client needs to pay on contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Fill in the blank: A _______ certificate enables a company to be paid for materials off site.

A

vesting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does the day work schedule cover?

A

Work that needs to be done by day work due to unforeseen circumstances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is included in the materials on site schedule?

A

Getting materials on and off site, covering for unsuspecting changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

True or False: A CVI must be recorded in writing to the client within 5 days.

17
Q

What is the role of a day work sheet?

A

To record day work events for payment assistance

18
Q

What is the purpose of the measured work section in valuations?

A

To account for drawings/specifications already decided but with extras added

19
Q

What is a variation schedule?

A

A record of changes requested by the client