Tender Activities (some procurement) Flashcards
Learn traditional PoW Stage 4 activities
Time for Pre-qualification questionnaire in public procurement.
30 days from date of dispatch of OJEU notice (if its over the £4.3million threshold). Can be reduced to 15 days if it meets certain criteria.
Time for tender response in public procurement.
30 days or four weeks. Except in Competitive Dialogue when there are no set response for tender.
Design and build - if design is not developed then 3-4 months maybe required
Time for pre-qualification questionnaire response in private procurement.
If its a traditional, single stage tender with no CDP - 14 days or 21 days is appropriate.
Can be extended if:
- Pre-qualification questionnaire is complex
- Contractor Design Portion is Included
- Process coincides with a holiday
What different procurement routes are available with RIBA 2013?
Traditional One stage Design and Build Two stage Design and Build Management Contract Contractor-led To be determined
When does tendering occur in each procurement route according to RIBA 2013?
Traditional - stage 4
One stage D+B - stage 3
Two stage D+B - stage 2 tender of preffered contractor for pre-construction services. Stage 4 building contract awarded based on contractor’s proposals
Management contract - stage 2 = building contract awarded - stage 4 = design info issued in agreed work packages for tender
Contractor-led - stage 2 and 3
What should be included in the tender Project Information Schedule (sent as part of preliminary enguiry)?
(this is a less essential question)
- details of the project and its estimated value
- the employer, the professional team, and contact points
- the tendering procedure to be used
- the programme
- CDP design
- BIM requirements
- Contract to be used and any amendments
- Contract Particulars - details of Collateral Warranties and Insurances
- criteria of pre-selection including weightings and order of importance.
- the basis of contract award (lowest price or price and quality)
Time for tender response in private procurement.
If its a traditional, single stage tender with no CDP - min 28 days.
Subject to PC Regulations this can be extended to 35 days.
How many tenderers should you invite?
Generally 3 to 6.
Design and Build - no more than 4.
For public procurement:
- with negotiation = min 3
- restrictive procedures = min 5